Caltrain's petition for a waiver of compliance from certain FRA crash safety standards is on the federal docket as of Monday, January 25th. This marks the start of a 45-day comment period. All documents associated with the petition can be found under docket number FRA-2009-0124.
Obtaining this waiver is key to the transition from Caltrain's existing equipment to the latest European-style electric trains (which meet different but equally effective crash safety standards), and also blazes an important regulatory trail for the peninsula HSR project.
It will be interesting to watch what sorts of comments are received, e.g. from freight customers potentially dissatisfied by more restrictive operating hours (midnight to 5 AM) or from U.S.-based vehicle manufacturers who might fear the market being opened to European suppliers. Stay tuned.
26 January 2010
20 January 2010
Development Oriented Transit
The Draft EIR for the Transit Village project is currently open for public comment.
The plans are remarkable for their amazing lack of coordination with the high-speed rail project. The Transit Village FAQ dismisses the issue in one fell swoop:
How will the project affect the proposed high speed rail service?A recent article in the San Mateo Daily Journal, highlighting concerns about the project, failed to mention the high-speed rail issue even once.
The project will not affect the proposed high speed rail service because the project site design already incorporates the necessary space for the future high speed rail service.
Meanwhile, HNTB, the engineering firm in charge of the peninsula rail corridor, is actively considering several design alternatives that would widen the corridor to well over 100 feet at the San Carlos station. One of these alternatives is to run a pair of HSR tracks west of the existing station, right where the Transit Village buildings are planned. Perhaps this is a game of who gets there first, but no matter which way you slice it, four tracks plus platforms are going to exceed 100 feet in width.
The project EIR includes several site sections, an example of which is reproduced above superimposed with one of the HSR configurations currently under consideration. (Click for the complete diagram, drawn to scale, without any utility easements--i.e. as narrow as possible). If the railroad right of way is not expanded eastward into Old County Road and the adjoining East San Carlos neighborhood, then the required rail corridor will quite literally overlap with the planned buildings as shown in the figure. Short of an actual overlap, even close proximity would be unacceptable from an interior noise standpoint, and would preclude emergency vehicle access to the rear of the buildings. The inescapable conclusion:
The project will very much be affected by HSR, quite possibly up to eminent domain and demolition.
Anyone who says otherwise is trying to sell you a Transit Village. Who will pay for this egregious lack of foresight? Probably the suckers who buy the residential units, and the suckers who pay taxes to fund needlessly expensive right-of-way acquisition. Remember, this little soap opera will take place on land that is currently owned by Caltrain and SamTrans!
Why pull another San Mateo? Have Caltrain and SamTrans learned nothing about sacrificing valuable railroad right-of-way on the altar of cities' pet projects? Is somebody in Sacramento going to wake up and knock some heads together? Or is it on us to foot the bill after the mess is made?
11 January 2010
The Prescriptive Framework
The Palo Alto grassroots organization Citizens Advocating Responsible Railroad Design (CARRD) requested that these documents be shared with the public. The CHSRA may not have been especially keen to release them, but CARRD's push was persistent and successful.
Keeping in mind that a little knowledge can be a dangerous thing, a few up-front caveats are in order:
- These documents are guidelines authored by Parsons Brinckerhoff program management staff, ensuring that early designs for each section (performed by HNTB for San Francisco - San Jose) are consistent and compatible. They are not a "design bible" for detailed 100% engineering.
- The documents cover the entire state, which consists primarily of 220-mph very high speed, dedicated tracks. The peninsula is a different animal, with 125-mph top speeds in a shared corridor with Caltrain and freight trains, so use proper care when applying to or inferring conclusions about specific peninsula situations. The peninsula-specific memo (TM 1.1.7) is due for initial release in June 2010.
- The documents are a snapshot in time, as of January 2010.
| Document Number | Title | Type |
| Program | ||
| TM 0.0a | Design Terms and Acronyms | memo |
| TM 0.1 | 15% Design Scope | memo |
| TM 0.3 | CHSTP Basis of Design Report | memo |
| TM 0.5 | Coordination with Caltrans | memo |
| TM 0.7 | Design Submittal Protocol | memo |
| Infrastructure | ||
| TM 1.1.1 | Codes, Regulations, Design Standards, and Guidelines | memo |
| TM 1.1.2 | Design Life | memo |
| TM 1.1.4 | Mapping and Surveys | memo |
| TM 1.1.5 | CADD Guidelines | memo |
| TM 1.1.6 | Alignment Stds for Shared Use Corridor – LA to Anaheim | memo |
| TM 1.1.8 | Proposed Methodology for Demarcation of Territorial Subdivisions and Milepost Numerics | memo |
| TM 1.1.8 | Subdivisions Milepost Map | map |
| TM 1.1.10 | High Speed Equipment Structure Gauges | memo |
| TM 1.1.18 | Design Variance Guidelines | memo |
| TM 1.1.19 | 15% Capital Cost Method | memo |
| TM 1.1.21 | Typical Cross Sections for 15% Design | memo |
| TM 1.1.21 | Typical Cross Section Directive Drawings | drawing |
| TM 2.1.2 | Alignment Design Standards for High-Speed Train Operation | memo |
| TM 2.1.3 | Turnouts and Station Tracks | memo |
| TM 2.1.7 | Intrusion Protection | memo |
| TM 2.1.8 | Turnouts and Yard Tracks | memo |
| TM 2.2.2 | Station Program Design Guidelines (Policy) | memo |
| TM 2.2.3 | High-Speed Train Passenger Station Site Design Guidelines | memo |
| TM 2.2.4 | Station Platform Geometric Design | memo |
| TM 2.2.4 | Station Platform Directive Drawings | drawing |
| TM 2.3.2 | Structure Design Loads | memo |
| TM 2.3.3 | Design Guidelines for High-Speed Train Aerial Structures | memo |
| TM 2.3.3 | Aerial Structure Directive Drawings | drawing |
| TM 2.4.2 | Basic Tunnel Configuration | memo |
| TM 2.4.2 | Tunnel Configuration Directive Drawings | drawing |
| TM 2.6.7 | Earthwork and Track Bed Design Guidelines | memo |
| TM 2.7.4 | Utilities Requirements for 15% Design | memo |
| TM 2.9.1 | Geotechnical Investigation Guidelines | memo |
| TM 2.9.2 | Geotech Reports Preparation Guidelines | memo |
| TM 2.9.3 | Geologic and Seismic Hazard Analysis Guidelines | memo |
| TM 2.10.4 | Interim Seismic Design Criteria | memo |
| Systems | ||
| TM 3.1.1.1 | 2x25 kV Autotransformer System | memo |
| TM 3.1.1.3 | Traction Power Supply Sites | memo |
| TM 3.1.1.3 | Traction Power Supply Sites Directive Drawings | drawing |
| TM 3.1.5.3 | Utility Power Supply | memo |
| TM 3.2.1 | Overhead Contact System Requirements | memo |
| TM 3.2.1 | Overhead Contact System Directive Drawings | drawing |
| TM 3.2.3 | Pantograph Clearances | memo |
| TM 3.2.3 | Pantograph Clearances Directive Drawings | drawing |
| Operations | ||
| TM 4.1 | LOSSAN Concept Level Operation Feasibility Study | memo |
| TM 4.1.1 | Justification for Two Track Station Configuration – LA to Anaheim | memo |
| TM 4.2 | Phase 1 Service Plan | memo |
| TM 4.3 | Full Build Service Plan | memo |
| TM 4.3 Apx A1 | Full Build Service Plan, Stopping Patterns | appendix |
| TM 4.3 Apx A3 | Full Build Service Plan, String Lines | appendix |
| TM 4.3 Apx A4 | Full Build Service Plan, Equipment Cycles | appendix |
| Maintenance | ||
| TM 5.1 | Terminal and Heavy Maintenance Facility Guidelines | memo |
| TM 5.1 | Terminal and Heavy Maintenance Facility Directive Drawings | drawing |
| TM 5.2 | Maintenance Of Way Facility Directive Drawings | drawing |
| TM 5.3 | Summary Description of Requirements and Guidelines for: Heavy Maintenance Facility, Terminal Layup/Storage & Maintenance Facilities, and Right-of-Way Maintenance Facilities | memo |
| Rolling Stock | ||
| TM 6.1 | Selected Train Technologies | memo |
06 January 2010
The Tao of Timetables
Service is where it all begins, as demonstrated when Caltrain's Baby Bullet started operating in 2004. Because the Bullet increased speed and convenience, ridership soon grew by a third, and Caltrain was featured on the cover of industry journals. But the Baby Bullet was just a baby step compared to what might soon be possible, and Caltrain can't afford to rest on its laurels.
The only three things that will really matter for the future of Caltrain are service, service and service.
(photo by Christophe Dune)
Constructing the Ideal Caltrain Timetable
Timetables are admittedly boring, but they are a compact and efficient way to describe a transit service. Improvements to the service are best understood through their effect on the timetable. Caltrain passengers stand to benefit from several future service improvements that can be sorted into two categories: (a) service improvements that come "for free" as a result of electrification and swift new EMU trains, and perhaps more importantly (b) service improvements that require a little bit of planning, creativity, intelligence, and effort to pull off.
Caltrain is relentlessly focused on (a) and appears distressingly oblivious to (b).
Type (a) service improvements that can basically be taken for granted are:
- Quicker start-to-stop times, since EMUs are more powerful and lighter than today's anemic and heavy diesel trains. The time savings from faster acceleration and braking really accrue when a train makes many stops.
- Shorter station dwell times, since EMUs will have more doors and level-boarding for rapid passenger loading and unloading.
- Faster top speeds, since the peninsula corridor will be grade-separated and use a modern signalling system shared with HSR. While acceleration is far more important than top speed, improving from today's 79 mph speed limit to about 100 mph does yield marginal benefits.
- Clockface scheduling, known in german-speaking countries as Taktverkehr (literally, "traffic to a beat"). In a clockface schedule, every train runs on a periodic timetable with a regular stopping pattern that repeats at some fraction or multiple of an hour (e.g. every 15, 30 or 60 minutes). In Switzerland, the entire country runs on a regular beat. Clockface scheduling eliminates annoying Caltrain questions such as "When is the next train coming?" or "Does it stop where I'm going?" A clockface schedule takes all the guesswork out of taking the train by allowing simple memorization of the timetable (e.g. :07 past the hour, every 15 minutes) Clockface scheduling is also a key enabler of intermodal connections. Connecting feeder services, whether bus, employee shuttle, light rail, HSR, etc. can be synchronized to the "beat" for quick, hassle-free transfers.
- Zero-wait transfers between local and express trains, so customers at smaller station stops can benefit from fast express service to the destination of their choice. Zero-wait transfers extend the benefit of express service to a much wider selection of origin and destination pairs. A zero-wait transfer means that an express train overtakes a local at zero speed, on the opposite side of the same platform. Passengers simply walk across the platform to switch to a faster or slower train, as suits their destination. Overtaking at zero-speed enables such transfers in the first place; if one were to wait for the express, the time savings from the express would evaporate before they could provide any benefit.
- Two, or maximum three, station stopping patterns, for simplicity. Customers no longer fret whether any given train will stop at their destination; no more agonizing Caltrain questions like "Should I get on this train or the next?" or "Does this train serve the stop where I'm going?," no more squinting at the timetable. Caltrain conductors would no longer make long-winded and repetitive announcements about upcoming stops and which stations will or won't be skipped.
String Theory
To think about timetables without having to stare at big tables of numbers, it helps to use a graphical representation of rail traffic known as a string graph (also known as a stringline diagram). Traffic is displayed as a time-distance graph with time along one axis and stations (distance) along the other. The movement of each train is represented by a string that connects each station according to the time intervals required to move from one station to the next. In effect, a string graph is the visual equivalent of a timetable. For example, the weekday morning Caltrain timetable is shown in the string graph at right. There are many kinds of strings, each corresponding to a different stopping pattern; the irregular pattern makes it difficult to memorize the timetable between any two stations. The red strings represent Baby Bullet express traffic, and the blue strings represent slower trains. When the lines cross (as circled on the diagram), one train overtakes the other. Today this can only happen in Sunnyvale or Brisbane, where Caltrain already has four tracks.Going back to our list of ideal timetable features, we can construct a string graph that includes them all. In the real world of operations planning, this is done using sophisticated simulation software, and needs to take into account detailed train performance, speed limits, curves, signal block lengths, off-nominal conditions, and knitting together with the HSR timetable (itself a complicated mess; see pages 16-24).
To first order, it can be done with a spreadsheet. Download a Caltrain string graph (385 kB Excel spreadsheet) to play with it.
The resulting Caltrain timetable is shown in the string graph at right, screen-grabbed directly from the spreadsheet. This string graph shows an example timetable, at a relatively sparse 6 trains per hour, with the following features:- 15-minute local interval
- 30-minute express interval
- Fast acceleration using 90 mph EMUs
- 45-second platform dwell times
- Zero-speed cross-platform overtake at Redwood City
The Service Improvement Table
The best way to convey an improvement plan in a way that the average person understands is to publish a service improvement table, an example of which is shown at right. (This example table does not show every station pair; for brevity, it shows a sampling of 10 stations.) This table is built by simply comparing the old and new string graphs. For each station pair along the peninsula, the improvement table shows how many more trains per hour connect the station pair, and how much quicker they are than today. This table is constructed by comparing the string graph of today's timetable with the string graph we constructed above.The table is a quantitative, objective measure of the degree to which service is improved. All capital improvements on the peninsula corridor should be evaluated and prioritized by their effect on the service improvement table.
Marketing 101
Memo to Caltrain: nobody really cares about "growth" or "advanced technology" or "flexible equipment" or "power facilities", or even "less pollution" as trumpeted in the latest electrification update. Those are entirely the wrong selling points. What customers most care about is getting quickly and conveniently from point A to point B.
Damn the pantographs, what you need to sell and deliver is a service plan.
When people ask "what's in it for me", show them the service improvement table for where they live and work. When people worry about the disruption from the peninsula HSR project, they can see that some benefits actually trickle down meaningfully and measurably to each and every city along the Caltrain corridor. Put this table in front of city council members up and down the peninsula. Publish it in local newspapers. Make brochures. Drop leaflets. When Burlingame gets worked up about grade separations, explain to them that service at Broadway will go from none at all to a train every 15 minutes. When Palo Alto frets about community division, show them how California Avenue will see a quadrupling of service, and will be 9 minutes closer to Millbrae.
A Litmus Test
The dirty little secret is that all the service improvements described above could have been realized without HSR, requiring only a few miles of strategically placed track amplification to enable a mid-peninsula overtake, and using capital improvement funds in a targeted fashion that measurably improves service. (Instead, Caltrain is plowing $300 million into the San Bruno grade separation, which provides zero service improvement, while claiming it is fiscally doomed without HSR).
The peninsula HSR project, which continues to be engineered for extremely high levels of service (despite lowered ridership estimates), will consume precious resources that currently belong to Caltrain--in particular, key portions of its corridor. Constructing HSR in a manner that precludes the above schedule, or something similar to it (i.e. clockface schedules with mid-line overtakes) from being reliably operated will forever stunt the future of the peninsula commute. That can rightly be considered totally unacceptable.
The timetabling criteria outlined in this article form an objective litmus test for an important question that should linger in the minds of peninsula residents: MOU notwithstanding, is Caltrain getting screwed over by the HSR project? Armed with this knowledge, you can be the judge.
04 January 2010
CSS Game Plan
The Peninsula Rail Program recently distributed follow-up materials (1.5 MB PDF) to the Context-Sensitive Solutions (CSS) workshop held in November.
The included schedule reveals that the Draft Alternatives Analysis Report is delayed from January to late February / early March, compressing the environmental review schedule against the late 2012 shovel-readiness deadline. As recently as December 10th, this document had been "on schedule" for release this month.
CSS stakeholders have expressed a multitude of concerns and ideas, ranging from quite reasonable to off-the-wall wacky; they must be read to be appreciated. Exactly how this laundry list of CSS concerns relates to the environmental Scoping Report is unclear. Perhaps the AA will be driven by the scoping report and the CSS workshops, which might explain the delay.
The included schedule reveals that the Draft Alternatives Analysis Report is delayed from January to late February / early March, compressing the environmental review schedule against the late 2012 shovel-readiness deadline. As recently as December 10th, this document had been "on schedule" for release this month.
CSS stakeholders have expressed a multitude of concerns and ideas, ranging from quite reasonable to off-the-wall wacky; they must be read to be appreciated. Exactly how this laundry list of CSS concerns relates to the environmental Scoping Report is unclear. Perhaps the AA will be driven by the scoping report and the CSS workshops, which might explain the delay.