06 January 2010

The Tao of Timetables

Amid all the hoopla about high-speed rail and quadruple tracking on the peninsula corridor, it's easy to miss the original point: to convey people from point A to point B as quickly and conveniently as possible. The peninsula rail improvements aren't just about pouring concrete and running zoomy trains; they ought to be about providing a service, especially to the dominant users of the corridor, namely local commuters and travelers, people who live and work right here on the peninsula. This important constituency is too often eclipsed by the bright spotlight shining on statewide high-speed rail.

Service is where it all begins, as demonstrated when Caltrain's Baby Bullet started operating in 2004. Because the Bullet increased speed and convenience, ridership soon grew by a third, and Caltrain was featured on the cover of industry journals. But the Baby Bullet was just a baby step compared to what might soon be possible, and Caltrain can't afford to rest on its laurels.

The only three things that will really matter for the future of Caltrain are service, service and service.
(photo by Christophe Dune)

Constructing the Ideal Caltrain Timetable

Timetables are admittedly boring, but they are a compact and efficient way to describe a transit service. Improvements to the service are best understood through their effect on the timetable. Caltrain passengers stand to benefit from several future service improvements that can be sorted into two categories: (a) service improvements that come "for free" as a result of electrification and swift new EMU trains, and perhaps more importantly (b) service improvements that require a little bit of planning, creativity, intelligence, and effort to pull off.

Caltrain is relentlessly focused on (a) and appears distressingly oblivious to (b).

Type (a) service improvements that can basically be taken for granted are:
  1. Quicker start-to-stop times, since EMUs are more powerful and lighter than today's anemic and heavy diesel trains. The time savings from faster acceleration and braking really accrue when a train makes many stops.

  2. Shorter station dwell times, since EMUs will have more doors and level-boarding for rapid passenger loading and unloading.

  3. Faster top speeds, since the peninsula corridor will be grade-separated and use a modern signalling system shared with HSR. While acceleration is far more important than top speed, improving from today's 79 mph speed limit to about 100 mph does yield marginal benefits.
Those are very nice, but they're just the low-hanging fruit. Type (b) service improvements are less obvious, but deliver enormous benefits for passengers. They include:
  1. Clockface scheduling, known in german-speaking countries as Taktverkehr (literally, "traffic to a beat"). In a clockface schedule, every train runs on a periodic timetable with a regular stopping pattern that repeats at some fraction or multiple of an hour (e.g. every 15, 30 or 60 minutes). In Switzerland, the entire country runs on a regular beat. Clockface scheduling eliminates annoying Caltrain questions such as "When is the next train coming?" or "Does it stop where I'm going?" A clockface schedule takes all the guesswork out of taking the train by allowing simple memorization of the timetable (e.g. :07 past the hour, every 15 minutes) Clockface scheduling is also a key enabler of intermodal connections. Connecting feeder services, whether bus, employee shuttle, light rail, HSR, etc. can be synchronized to the "beat" for quick, hassle-free transfers.

  2. Zero-wait transfers between local and express trains, so customers at smaller station stops can benefit from fast express service to the destination of their choice. Zero-wait transfers extend the benefit of express service to a much wider selection of origin and destination pairs. A zero-wait transfer means that an express train overtakes a local at zero speed, on the opposite side of the same platform. Passengers simply walk across the platform to switch to a faster or slower train, as suits their destination. Overtaking at zero-speed enables such transfers in the first place; if one were to wait for the express, the time savings from the express would evaporate before they could provide any benefit.

  3. Two, or maximum three, station stopping patterns, for simplicity. Customers no longer fret whether any given train will stop at their destination; no more agonizing Caltrain questions like "Should I get on this train or the next?" or "Does this train serve the stop where I'm going?," no more squinting at the timetable. Caltrain conductors would no longer make long-winded and repetitive announcements about upcoming stops and which stations will or won't be skipped.
What would an ideal Caltrain timetable look like with all of these improvements? We'll soon find out, but first, a small detour through...

String Theory

To think about timetables without having to stare at big tables of numbers, it helps to use a graphical representation of rail traffic known as a string graph (also known as a stringline diagram). Traffic is displayed as a time-distance graph with time along one axis and stations (distance) along the other. The movement of each train is represented by a string that connects each station according to the time intervals required to move from one station to the next. In effect, a string graph is the visual equivalent of a timetable. For example, the weekday morning Caltrain timetable is shown in the string graph at right. There are many kinds of strings, each corresponding to a different stopping pattern; the irregular pattern makes it difficult to memorize the timetable between any two stations. The red strings represent Baby Bullet express traffic, and the blue strings represent slower trains. When the lines cross (as circled on the diagram), one train overtakes the other. Today this can only happen in Sunnyvale or Brisbane, where Caltrain already has four tracks.

Going back to our list of ideal timetable features, we can construct a string graph that includes them all. In the real world of operations planning, this is done using sophisticated simulation software, and needs to take into account detailed train performance, speed limits, curves, signal block lengths, off-nominal conditions, and knitting together with the HSR timetable (itself a complicated mess; see pages 16-24).

To first order, it can be done with a spreadsheet. Download a Caltrain string graph (385 kB Excel spreadsheet) to play with it.

The resulting Caltrain timetable is shown in the string graph at right, screen-grabbed directly from the spreadsheet. This string graph shows an example timetable, at a relatively sparse 6 trains per hour, with the following features:
  • 15-minute local interval
  • 30-minute express interval
  • Fast acceleration using 90 mph EMUs
  • 45-second platform dwell times
  • Zero-speed cross-platform overtake at Redwood City
It's quite easy to change these assumptions using the spreadsheet to see what happens. At a glance, the timetable certainly looks more symmetrical and orderly, but how does one meaningfully compare old and new?

The Service Improvement Table

The best way to convey an improvement plan in a way that the average person understands is to publish a service improvement table, an example of which is shown at right. (This example table does not show every station pair; for brevity, it shows a sampling of 10 stations.) This table is built by simply comparing the old and new string graphs. For each station pair along the peninsula, the improvement table shows how many more trains per hour connect the station pair, and how much quicker they are than today. This table is constructed by comparing the string graph of today's timetable with the string graph we constructed above.

The table is a quantitative, objective measure of the degree to which service is improved. All capital improvements on the peninsula corridor should be evaluated and prioritized by their effect on the service improvement table.

Marketing 101

Memo to Caltrain: nobody really cares about "growth" or "advanced technology" or "flexible equipment" or "power facilities", or even "less pollution" as trumpeted in the latest electrification update. Those are entirely the wrong selling points. What customers most care about is getting quickly and conveniently from point A to point B.

Damn the pantographs, what you need to sell and deliver is a service plan.

When people ask "what's in it for me", show them the service improvement table for where they live and work. When people worry about the disruption from the peninsula HSR project, they can see that some benefits actually trickle down meaningfully and measurably to each and every city along the Caltrain corridor. Put this table in front of city council members up and down the peninsula. Publish it in local newspapers. Make brochures. Drop leaflets. When Burlingame gets worked up about grade separations, explain to them that service at Broadway will go from none at all to a train every 15 minutes. When Palo Alto frets about community division, show them how California Avenue will see a quadrupling of service, and will be 9 minutes closer to Millbrae.

A Litmus Test

The dirty little secret is that all the service improvements described above could have been realized without HSR, requiring only a few miles of strategically placed track amplification to enable a mid-peninsula overtake, and using capital improvement funds in a targeted fashion that measurably improves service. (Instead, Caltrain is plowing $300 million into the San Bruno grade separation, which provides zero service improvement, while claiming it is fiscally doomed without HSR).

The peninsula HSR project, which continues to be engineered for extremely high levels of service (despite lowered ridership estimates), will consume precious resources that currently belong to Caltrain--in particular, key portions of its corridor. Constructing HSR in a manner that precludes the above schedule, or something similar to it (i.e. clockface schedules with mid-line overtakes) from being reliably operated will forever stunt the future of the peninsula commute. That can rightly be considered totally unacceptable.

The timetabling criteria outlined in this article form an objective litmus test for an important question that should linger in the minds of peninsula residents: MOU notwithstanding, is Caltrain getting screwed over by the HSR project? Armed with this knowledge, you can be the judge.

04 January 2010

CSS Game Plan

The Peninsula Rail Program recently distributed follow-up materials (1.5 MB PDF) to the Context-Sensitive Solutions (CSS) workshop held in November.

The included schedule reveals that the Draft Alternatives Analysis Report is delayed from January to late February / early March, compressing the environmental review schedule against the late 2012 shovel-readiness deadline. As recently as December 10th, this document had been "on schedule" for release this month.

CSS stakeholders have expressed a multitude of concerns and ideas, ranging from quite reasonable to off-the-wall wacky; they must be read to be appreciated. Exactly how this laundry list of CSS concerns relates to the environmental Scoping Report is unclear. Perhaps the AA will be driven by the scoping report and the CSS workshops, which might explain the delay.

31 December 2009

Focus on: Mountain View

Mountain View, home to some of the biggest names in Silicon Valley, is the third busiest Caltrain stop behind San Francisco and Palo Alto, and serves as a transfer point between Caltrain and the VTA light rail system. (photo by LazyTom.) The city has so far adopted a conciliatory attitude towards the high-speed rail project, unlike several cities to the north. In its scoping comments (p. 90), Mountain View first and foremost asks to be considered as a candidate for a peninsula HSR stop, citing its strategic location, transit connections, and easily accessible freeway network. The CHSRA's preliminary alternatives analysis for the first time featured Mountain View as a potential peninsula HSR station.

The railroad right-of-way through Mountain View parallels Central Expressway, a four-lane divided highway that is part of Santa Clara County's expressway network. This inherently gives the peninsula rail corridor a less residential character than in communities to the north, although several new housing developments have been built near the tracks in recent years, with more planned in the vicinity of the San Antonio Caltrain station. The latter station, opened in 1999, replaced the primitive stop formerly located at Rengstorff Avenue with what was billed as a model transit-oriented development.

Vertical Profile

The vertical profile of the existing Caltrain tracks is shown in the diagram below, created from Caltrain track survey data. The tracks slope gently, with the southern end of town a full 50 feet higher than the north. The slope is steepest (a bit over 0.6%) in the section between Castro St. and the Rte. 85 overpass, near the downtown station.


There are just two grade crossings remaining in Mountain View: Rengstorff Avenue and Castro Street.

The city has been planning a grade separation at Rengstorff Avenue since 2002, which is currently entering the environmental review process independently of high-speed rail. The city's preferred alternative (see feasibility study in PDF Attachment 2) calls for Rengstorff and the nearby intersection with Central Expressway to be depressed under the tracks. The $45 million plan already includes a corridor expansion to four tracks, as shown in the figure at right. Other design alternatives were eliminated: trenching the tracks at this location would have been complicated by the nearby Permanente Creek, and residents were concerned about the visual impact of elevated tracks. Nevertheless, the HSR scoping comments submitted by the city (see p. 95) ask that all vertical alignment alternatives be re-examined for the Rengstorff grade separation. Since the technical and community constraints have not changed at this location, the HSR alternatives analysis is likely to be consistent with the city's prior study.

That leaves the crossing at Castro Street in the downtown area, the most challenging design puzzle in Mountain View, where only one vertical alignment solution stands out as realistically feasible. The options that will probably not be practical are:
  • A deep bore tunnel. While technically feasible, such a tunnel would be prohibitively expensive and difficult to build because the entire Mountain View train station would need to be sunk below grade, including 1/4 mile platforms if the city is selected as an HSR stop.

  • A cut-and-cover tunnel or trench. The rails would need to be sunk 25 to 30 feet deep to pass under Castro Street, but the natural slope of the terrain to the south would require a steep 3% rise back to grade level at the Stevens Creek, potentially compromising the ability of freight trains to use the corridor. (This assumes re-routing the creek is not practical.)

  • An at-grade alignment. The high train speeds would require the permanent closure of Castro Street, or the construction of a bridge over the tracks with extensive impacts to the 100 block of the historic downtown and businesses on Moffett Blvd. Either way, Castro would no longer connect to Central Expressway.

That leaves just one reasonable option: a split grade separation with the tracks elevated about 15 feet above grade and Castro Street sunk by about 5 feet. Sidewalks could stay at the current grade level, and the station would be elevated, not unlike the existing design at Belmont. To the north, the tracks would require a 2% grade to duck under the bridge at Shoreline Blvd. To the south, the tracks could run level (which is of benefit for building a new train station) to meet the rising natural grade, returning to ground level at the Stevens Creek. The resulting vertical profile is shown in the diagram below, in green; compare to the infeasible below-grade alignment shown in red.


While Caltrain and high-speed rail would comfortably handle this vertical profile, a rigid adherence to a 1% grade limit for the benefit of freight trains would likely require Castro Street be closed entirely to road traffic.

Horizontal Alignment

The Caltrain right of way is quite wide throughout Mountain View, with 75 - 100 feet available to build out the corridor to four tracks. The relatively sharp curve at San Antonio (the #8 worst curve on the peninsula) just barely allows 125 mph operation, although it could be straightened within the confines of the right of way. Does that mean Mountain View will easily accommodate an expanded, four-track, high-speed corridor? Sadly, no.

In the late 1990s, Caltrain agreed to let VTA and the city construct a light rail extension on its right of way. The light rail system now runs alongside the Caltrain tracks for about one mile, ending at a 50-foot wide terminal with expansive storage tracks near Castro Street (photo by LazyTom). On the western side of the Caltrain tracks, the city built a "transit center" to replace the dingy asphalt strip that previously served as a Caltrain platform. This $20 million intermodal facility was completed in 2002 with a new plaza and modern-day replica of Mountain View's old train depot, which might have earned a spot in a register of historic places had it not been razed in 1959. All this recent construction consumed a large portion of the available right of way, where ample space to build four tracks existed as recently as 1998. Not surprisingly, the city clings to this new civic infrastructure and suggests among other options that HSR be routed via the Central Expressway median--never mind that $20 million is a relative pittance in the context of the peninsula HSR project.

Further south, one southbound lane of Central Expressway will likely be taken to route the VTA track east of the bridge support pillars at Rte. 85 and Whisman, freeing up space for the four-track peninsula corridor.

The light rail situation is further complicated by (a) VTA's inexplicable ambition to double-track the short section of single track that encroaches on the Caltrain corridor, (b) the possible need to maintain freight train access to the Moffett Drill Track (see docket FRA-1999-6254 ; the switch that connected the VTA tracks to the peninsula corridor was recently dismantled, but the Moffett spur is not formally abandoned), and (c) the difficulty of relocating the Evelyn VTA station--incidentally second-to-last in ridership on the entire light rail system, with roughly 60 daily passengers. All three of these factors need to be examined with a critical eye towards who will pay and who will benefit.

Further north, another pinch point exists near the San Antonio station, where the San Antonio Road overpass (a 1960s structure that Caltrans lists as a deficient bridge) does not provide sufficient horizontal clearance for four tracks. The nearby pedestrian underpass would also require modification, likely as part of its extension across Central Expressway to the planned residential redevelopment of Hewlett Packard's former Mayfield campus. It goes without saying that the San Antonio platforms will need to be rebuilt, just like anywhere else on the peninsula.

Downtown Done Right

To visualize downtown "done right," download Mountain View 3D Model (2.2 Mb) for Google Earth. All the illustrations in this section are taken directly from this model, built by Richard Mlynarik.

While Mountain View's transit center is billed as an intermodal, accessible facility, there is vast room for improvement in passenger circulation. The challenge of designing a rail alignment that overcomes the twin obstacles of Castro Street and the light rail tracks presents an opportunity to improve Mountain View's transit center by creating a modern, functioning gateway into downtown. While the construction impact would indeed be frustrating, especially so soon after the area was rebuilt, this would simply reflect the haphazard manner in which the existing facility was planned, with little regard to future HSR requirements or effective pedestrian circulation.

Currently, the light rail tracks end on an unpleasant concrete island hemmed in by Central Expressway and the Caltrain tracks, requiring a circuitous route for pedestrians to access the trains. Centennial Plaza, the faux-depot and the bus loop cut off the Caltrain platforms from downtown. All passengers wishing to transfer between buses and trains must use crosswalks.

There is surely a better way. One possible redesign of the Mountain View Transit Center is described below. It is an exercise to achieve the best possible transportation functionality, providing these specific benefits:

  • Keeps Castro open to all traffic
  • Provides direct, elevator-free access from Caltrain/HSR platforms to sidewalks on both sides of Castro, without circuitous detours
  • Places the VTA light rail terminus in Centennial Plaza, where it meshes intimately with the pedestrian fabric of downtown
  • Allows direct platform-to-platform, passenger-friendly transfers between light rail, Caltrain locals and expresses, HSR, buses and employee shuttles--without the need for an umbrella during the rainy season
  • Locates station amenities such as ticketing, bathrooms, snacks, etc. at the crossroads of pedestrian traffic
  • Provides station parking under the tracks, reducing the need for unsightly parking structures
  • Does not force bus passengers to use a crosswalk
The resulting configuration is a four-track, two-platform Caltrain / HSR station, elevated over Castro Street. The light rail station slants diagonally underneath the elevated tracks, with the trolleys pulling right up to the corner of Castro and Evelyn in a sunken Centennial plaza. (Light rail requires the same 16-foot vertical clearance as road traffic on Castro). The twin Caltrain / HSR island platforms are extended north over Castro, enabling direct access to sidewalks on both sides and a platform-to-platform transfer between all transit modes.



















Centennial Plaza looking east
Evelyn looking north to Castro
Castro & Central looking south

View from northbound Central Expressway


For additional views and detail, download the 3D model for Google Earth.

What happened to the retro-faux-depot? Remember, this design is an exercise in form following transportation function. In 1895, the depot would have housed important functions such as mail and baggage handling, signaling staff, and a telegraph operator. Today, those functions are obsolete, so the depot building has no place or purpose. It's gone, for the greater good of functional 21st-century transportation. Architecturally, there are far more exciting possibilities that enhance rather than impede functionality.

Regardless of the details of how exactly HSR is integrated with Mountain View's transit center, one thing is clear: the high-speed rail authority's charter is to build HSR, period. Ensuring that the intermodal connections at Mountain View can live up to their potential will largely be up to the city and its citizens, who ought to take strong initiative to ensure it's done right--without letting their judgment be unduly clouded by the $20 million they spent this past decade.

NOTE: This post will be updated continuously, as warranted by additional information or new events relating to Mountain View.

20 December 2009

Constructions Methods Booklet

A neat little Constructions Method Booklet (2.8 MB PDF) authored by Peninsula Rail Program director Bob Doty was recently distributed at a community meeting. This booklet is currently undergoing an update, which will be posted under the Resources section as soon as it's available. In the meantime, the booklet provides some good general background for making sense of the draft Analysis of Alternatives document that will be published within the next couple of months. The draft AA will be the first time that peninsula residents are given specific design information resulting from the preliminary engineering work that has been underway since the summer.

As the caveat clearly states: This information is provided for discussion purposes only and includes data and assumptions representative of similar programs. The actual requirements for the Peninsula Rail Corridor have not been established.

17 December 2009

On Width

Update: a different reliable source indicates the land impacts along the corridor were determined (and minimized) by laying out an 87-foot wide corridor, measured over the fence footings on either side. That was a nominal value, with narrower design exceptions possible in highly-constrained locations.

Original Post: When we reviewed just how wide the Caltrain corridor is, we assumed a 75-foot minimum width for a four-track rail corridor, measuring from fence to fence. New figures, obtained from reliable sources, indicate typical dimensions will be quite a bit more:
  • 15' (4.6 m) Caltrain track spacing (measured center-to-center)
  • 16'6" (5 m) HSR track spacing, or between HSR and Caltrain tracks
  • The kicker: 23'6" to 28'6" between the outer track center line and the boundary fence, to allow for third-party utility easements (as already exist in many places along the Caltrain corridor), overhead electrification poles, maintenance walkways, drainage structures, etc.
Worst case, that adds up to 28'6" + 16'6" + 16'6" + 16'6" + 28'6" = 106'6" (32.5 m). The best case, with Caltrain tracks in the middle, adds up to 23'6" + 16'6" + 15' + 16'6" + 23'6" = 95' (29 m). Both figures are measured fence-to-fence, presumably for a situation where all four tracks run at ground level.

Time to Panic?

Well, maybe not quite yet.

These figures are quite likely quoted for the nominal situation, where plenty of land is available. Indeed, more than two-thirds of the peninsula rail corridor is 100 feet or wider, allowing generous side clearances. Caltrain's own environmental documents, drafted for the electrification project long before HSR came along, include the typical four-track section reproduced at right, with a nominal fence-to-fence width of 89 feet.

Then again, the HSR numbers are incredibly generous by international standards, and probably accommodate vehicular access along both sides of the right of way. (A Department of Homeland Security Crown Victoria is 6'6" wide, for reference.)

The minimum legal side clearances in California are dictated in CPUC General Order 26-D. The absolute minima are 14' between track centers and 10' side clearances to the edge of the right-of-way. Caltrain's engineering standards reflect these constraints in a clearance drawing. None of these standards envision trains running at 125 mph and above, since those have never existed in California. Better numbers can be gleaned from foreign standards, for example the German Eisenbahn, Bau- und Betriebsordnung (EBO). That particular standard requires the following side clearances:
  • A danger zone (free of any obstructions such as poles, walls, etc.) of 2.5 m (8'2"), measured from the track center line, for train speeds less than 160 km/h (100 mph) and 3.0 m (10') for greater speeds.
  • Outside of the danger zone, a 0.8 m (2'6") space for rail personnel to take refuge at a safe distance from trains
  • The danger zones of neighboring tracks may overlap, with tracks spaced 4 m (13') for speeds less than 250 km/h (150 mph) and 4.2 m to 4.5 m (14' to 15') above. Since European trains are about a foot narrower than ours, that's roughly consistent with the 15-foot minimum already in use on the peninsula.
Where the Caltrain corridor is too narrow (such as in certain sections of San Mateo or Menlo Park), technical and political considerations make it probable that the HSR project will prefer adapting to the local constraints before seizing property and revving up the bulldozers.

If one had to make an educated guess about the minimum allowable corridor width, as opposed to the typical width, it would likely be closer to the values in the German EBO and/or the European Technical Specifications for Interoperability (TSI). Using the 16'6" track spacing mentioned above, that comes out to 0.8 m + 3 m + 5 m + 5 m + 5 m + 3 m + 0.8 m = 22.6 m, or 75 feet. The actual minimum for the peninsula corridor is likely to be spelled out in the upcoming draft Analysis of Alternatives.

Those figures are only valid for an alignment at grade level, which is the narrowest option. Raising or lowering the tracks requires additional width for construction.