Showing posts with label grade crossings. Show all posts
Showing posts with label grade crossings. Show all posts

28 September 2024

Cars on the Tracks

Cars turning off from a grade crossing onto the tracks are a perennial problem for Caltrain, often resulting in multi-hour cascading delays or worse, dangerous collisions. The statistics are shocking: from 2020 through 2023, there were 183 recorded incidents of "vehicle track incursions," of which more than half occurred at just five crossings as shown in the Caltrain bar chart at right.

Caltrain has tried mightily to take measures against this human error. It's useful to view these attempts through a risk management lens: the risk is the product of the probability of a vehicle entering the tracks, multiplied by its consequence.

Reducing Probability

We can do a little bit of Street View tourism to see what solutions have been attempted so far to reduce the probability of a vehicle track incursion:

Paint stripes give visual feedback, but such road markings are often not observed by the sort of driver who might not see that they are turning onto tracks.
Reflectors and Botts Dots keep a low profile to fit under passing trains, while giving visual and steering wheel feedback. In the gauge, they get beat up by equipment dragging under freight trains. This example is at Castro Street in Mountain View.

Rumble strips, similar to above solution, at Mission Bay Drive in San Francisco.
Solar reflectors go one step further by lightning up at night. The small solar cell at the top charges a battery that powers red LED lights when it is dark. This example is at 16th Street in San Francisco.
Speed bumps provide slightly more steering wheel feedback. This example is at Mission Bay Drive in San Francisco.

All of these measures are probably effective to some extent, but they won't stop a vision-impaired or inebriated or inexperienced driver, especially when they are mindlessly following GPS directions to turn onto a street that immediately parallels the tracks, a common feature of the grade crossings with the highest incidence of vehicle track incursions.

Reducing Consequence

Before we can discuss reducing the consequence of a vehicle track incursion, we need to acknowledge just what the consequence is: at a minimum, the vehicle becomes stranded on the tracks, requiring extrication by a tow truck. At worst, there is a dangerous collision with a train.

Most vehicles will end up high-centered if they blunder onto the tracks because the rail is 7" 5/16 tall and the center of concrete ties dips lower, resulting in easily 9" of height difference between the surface of the ties and the top of the rail. This height exceeds the ground clearance of most SUVs. Once high-centered, a vehicle with open differentials (i.e., not-Jeep) loses traction and becomes stranded. The driver is unable to correct their mistake, and when they try, they often just make it worse by driving further onto the tracks.

Currently, Caltrain applies no mitigation to this consequence. Their entire risk mitigation approach to vehicle track incursions relies on prevention, by reducing the probability while accepting the consequence that a stranding is inevitable. It is not!

Anti-trespass panels in New York, on Metro North.
Photo by Daniel Case.

Anti-trespass panels can mitigate the consequence of a vehicle track incursion through two mechanisms: 

1) very strong vibratory feedback that the vehicle has departed the road, likely to induce brake application on a reflexive basis and avoiding a deeper incursion.

2) reduced height difference between the rail and surrounding surfaces, enabling a vehicle with low ground clearance to maneuver without becoming high-centered. The driver can self-extricate the vehicle.

While these rubber panels are primarily intended to prevent pedestrian trespassing, they would likely also work for cars if laid down for about 30 feet beyond the edge of a crossing. They are a passive solution with low operating cost, certainly a much more effective mitigation than CCTV or intrusion sensors with alerts integrated into the signalling system. All these expensive and technology-heavy solutions may prevent a collision, but do nothing about the need for a tow truck or the resulting service disruption. This makes anti-trespass panels an ideal solution that best addresses the need of Caltrain riders to arrive on time.

The south side of Churchill Avenue in Palo Alto would make an excellent location for a pilot installation.

05 May 2019

Thoughts on Grade Separations

The emerging Caltrain business plan is broaching the issue of grade separations, a decadal process that has been underway, well, for decades. We're already 63% of the way there today, with another dozen new grade separation projects in various stages of planning or construction. Achieving a reasonable level of grade separation for the peninsula corridor is estimated to cost $8.5 - 11.1 billion, a shockingly large sum that we'll just round to $10 billion. As we try to grasp the enormity of that figure, here are some contrarian thoughts:

1) Don't spend train money on car projects. The benefit of grade separations accrues primarily to automobile travel, with the elimination of gate down time. An intensive grade separation program can eventually unlock additional operating slots for more trains and eliminate the occasional incident, yielding benefits to train riders. Some grade separations are necessary, such as when expanding to four tracks. In the short term, however, the greatest benefit is the removal of an inconvenience to drivers, which in our car-centric society is held as a worthy goal seemingly regardless of cost. Rail dollars are a lot scarcer than road dollars, especially in this era of federal disengagement, so the last project we should spend them on is a project that facilitates car travel with little improvement for train riders. Rail funding should be used to make real and measurable improvements to train service, a standard by which most grade separations rate poorly. So you still want a grade separation? Build it with road funding.

Anticipated gate down times,
under various scenarios in the
Caltrain business plan
2) Quit whining about gate down time. Caltrain put together a nice summary of gate down time, the number of minutes per hour that grade crossing gates block traffic during rush hours. Today the average is 11 minutes, and under future growth scenarios it could increase to 17 - 25 minutes, with a few crossings faring worse than average. If that sounds intolerable, think about a typical roadway intersection with a traffic light. If both roads are equally important, the "gate down time" of a traffic light is 30 minutes. If one road is more important, the lesser road (for example, Ravenswood Ave where it meets El Camino Real in Menlo Park) sees "gate down time" well in excess of 30 minutes, let's say 40 minutes per hour. Nobody is clamoring to grade separate the Ravenswood / El Camino road intersection. There's an obvious double standard here, and the guidelines for what qualifies as unacceptable delay should be set the same way as they are for the grade separation of a road intersection. Gate down time should only rarely, if ever, be the reason to build a new grade separation.

3) There are few economies of scale in grade separation. Doing them all as a package does not save money. The process we have, where local jurisdictions often exert tight control over every aspect of design and construction, does not lend itself to a one-size-fits-all approach. Each grade separation is different. Grade separation designs do not depend on each other in the majority of cases where they are widely spaced. While a corridor-wide strategy is important to have, the execution of that strategy and the securing of funding is inherently a city and county issue. If we are going to have a corridor-wide funding approach, it must go hand-in-hand with taking away local control. Jurisdictions that insist on local control should be left to figure out the funding on their own. Palo Alto, where interminable and futile discussions of tunnels continue to this day, should not be allowed to control the design process if their project is paid for through a corridor-wide funding measure.

4) If $10 billion is an okay expense, then there are far better ways to spend it. Especially with rail money at stake, there are much better ways to spend $10 billion than by building a lot of grade separations for cars that produce zero improvement to train service. There are a lot of good investments that should be made to improve the amount and speed of train service:
  • Extend all platforms to 8-car length. If you put all the platforms that Caltrain ever built in the last 20 years end to end, they would stretch about 5 miles long. This is not an expensive project; it can be done for about $0.05 billion. It should already be underway, but inexplicably isn't.
  • Convert the entire train fleet to 8-car EMUs, starting by exercising the rest of the existing Stadler contract option of another 59 cars, increasing the fleet to 24 trains. The diesels are retired from the peninsula, which is a condition for starting any level boarding projects. This costs about $0.4 billion.
  • Convert the entire system to level boarding to speed trips and improve punctuality. Depending on how this is done (high platforms or low platforms, or some combination thereof) and over how long a period of construction, this would cost about $0.5 - 1 billion.
  • Build a new EMU maintenance and storage facility near Blossom Hill (San Jose) and extend frequent electrified service through all of San Jose. Including any extortion by UPRR, the owner of the tracks, this ought to be feasible for less than $1 billion.
  • Build a new transit center in Redwood City to enable cross-platform transfers between locals and expresses. Call it $0.5 billion, and throw in the downtown grade separations for another $0.5 billion to allow four tracks.
  • Expand the EMU fleet to enable 8 train per hour peak service. Expanding the fleet to 32 trains would require another 64 EMU cars, for about $0.5 billion.
  • Extend the platforms at highly patronized express stops to 12 cars in length, and extend expresses to 12 cars. This would require extending about half the fleet by 4 cars, or another 64 EMU cars. Including platforms this might cost about $0.8 billion.
This isn't an exhaustive list, but unlike grade separations, all of these projects have immediate and measurable positive effects on the quantity and quality of service provided to riders. This list achieves most of Caltrain's "moderate growth" scenario but without HSR. The tally for all of these projects is still less than $5 billion, so if $10 billion for grade separations sounds at all palatable, this list ought to be a no-brainer.

Grade separations are nice, but their cost and benefit should be weighed very carefully on a case-by-case basis. The cost should be borne by who benefits. The business plan process will hopefully create the framework to have the difficult conversations about what not to pay for with rail funding. Grade separations should be built with highway funding unless there is a clear and measurable benefit to rail service.

08 December 2018

Grade Crossing Trouble Ahead

Grade crossing in Denver (photo: RTD)
Denver's RTD has been operating a new 25 kV electrified commuter railroad since 2016. There's a big problem with it: the grade crossings gates are down for too long, which the FRA and Colorado PUC consider hazardous because impatient motorists frustrated by a longer-than-expected wait may drive around the gates just as the train finally shows up. The problem has festered, with  millions spent on human flaggers to supervise traffic at each grade crossing, contractual acrimony leading to lawsuits, and in recent days a threat by the FRA to shut down the entire railroad until the issue is resolved.

What does any of this have to do with Caltrain? The peninsula corridor electrification project uses the same electrification technology installed by the same contractor (Balfour Beatty), uses the same positive train control technology installed by the same contractor (Wabtec), must contend with more than three times as many grade crossings, and therefore, faces the same looming grade crossing problem. For months, the issue has topped the list of risks that threaten the project, and the search for a viable solution is causing the electrification contractor to fall significantly behind schedule.

How grade crossings are supposed to work

The simplest way to activate a grade crossing is for the train to shunt a track circuit at some set distance before the crossing. This is known as a conventional track circuit warning system, and doesn't work well if different trains arrive at different speeds. The point where the crossing activates must be set far enough ahead to give the required warning time before the fastest train arrives at the crossing; this makes the gates stay down too long for slower trains.

The usual solution to this problem is a Constant Warning Time (CWT) system, which uses electrical signals sent through the track to sense the distance and speed of the approaching train. The grade crossing controller can then predict when to activate the crossing such that the warning time is approximately constant regardless of train speed. This is the type of warning system installed today on the many grade crossings of the peninsula rail corridor.

The FRA provides a nice overview discussion of how various types of grade crossings work. The applicable federal regulations are under 49 CFR Part 234.

What happened in Denver

Because the Denver system is electrified, there are large 60 Hz AC traction return currents (at safe low voltage!) commonly present in the rails when a train is nearby. These currents interfere with and prevent the use of a traditional Constant Warning Time system.

The contractor came up with a "smart" solution: the crossings have a traditional track circuit warning system overlaid with a wireless crossing activation system (WCAS) that interfaces with the positive train control system. Software sends wireless messages back and forth between the train computer and the crossing controller. The train and crossing enter into a contract: the train predicts when it will arrive at the crossing and promises not to get there any sooner, and the crossing commits to activate at some fixed time interval before the appointed arrival, staying closed until the train passes. Depending on the circumstance, the train may arrive at the crossing later than anticipated when the contract was entered into, resulting in extended gate down time. When WCAS is inoperative, the old-school track circuit takes over, also resulting in extended gate down time when a train is operating at less than maximum speed.

In early 2016, before the Denver train opened for revenue service, FRA and PUC inspectors found that the crossings activation times were inconsistent, with frequent occurrence of long gate down times and erosion of what is known as "credibility" of the warning system. Things went gradually downhill from there:
  • So as not to delay the much anticipated start of revenue service, the regulatory agencies granted a temporary waiver to allow RTD to begin operating without WCAS, on the condition that human flaggers supervise traffic at each affected crossing, at the expense of the contractor.
  • The contractor tried to tweak the WCAS software to make warning times more consistent. A fudge factor known as the "Approach Condition Adjustment Factor" (ACAF, so known because every fudge factor needs an acronym to sound legitimate) was applied based on the observed statistical distribution of warning times at each crossing.
  • In September 2017, the FRA gave RTD relief in its interpretation of the consistency required for gate downtime, relaxing its unofficial consistency criterion from +/-5 seconds or +/-10% of programmed warning time to +15/-5 seconds for RTD's system.
  • Performance of WCAS failed to satisfy the increasingly picky regulatory agencies. RTD began to penalize the contractor for failing to deliver a working grade crossing solution. FRA inspectors kept writing up excessive downtime violations.
  • The FRA forbade the start of revenue service on a newer rail line that has since been completed. The original plan to create quiet zones, where train horns are not used at grade crossings, was delayed indefinitely to the continuing aggravation of neighboring residents.
  • In September 2018, the contractor decided that the regulatory agencies had invented and enforced new consistency requirements that were not in the official regulations, and sued RTD claiming "force majeure" of a regulatory change. The complaint makes a fascinating read.
  • In October 2018, the FRA provided the latest inspection report (of many) showing continuing non-compliance with the -5/+15 second consistency tolerance.
  • On November 15th, 2018, the FRA fired off a letter indicating that it was fed up with the continuing grade crossing non-compliance, among other things, and threatened to shut down the entire commuter rail system by revoking the 2016 waiver.
  • RTD is lawyering up against the FRA, and submitted a strongly worded legal memorandum with numerous exhibits effectively claiming that the grade crossing problem exists solely in the imagination of the regulators. RTD provided evidence that other railroads (including Caltrain!) commonly experienced long gate down times in violation of the criteria imposed on RTD.
Whatever happens next is sure to be dramatic. The entire saga can be reviewed under docket FRA-2016-0028, which organizes all the documents exchanged between RTD and the FRA relating to the temporary operating waiver.

Some Observations
Measured distribution of 38255 grade
crossing activation times in Denver.
  1. Denver solved the wrong problem. They tried to invent a better mousetrap, something more sophisticated than a constant warning time grade crossing predictor. All they needed to do was to provide the same simple function with a substitute detection method that didn't rely on traditional audio-frequency AC circuits, which are incompatible with electrification. Instead, they decided to invent a better mousetrap involving lots of software, GPS, and wireless messaging, which naturally attracted regulatory scrutiny.
     
  2. Complexity is bad. Multiplying the number of interfaces and creating dependencies between elements of the system leads to expensive aerospace avionics-like hardware and software that is cumbersome to deploy, test and maintain. System complexity leads to a proliferation of strange and unanticipated corner cases and failure modes.
     
  3. Software can anticipate when to activate a crossing and prevent a train from showing up too soon, but there is no software in the world that can make a train show up on time.
     
  4.  Grade crossing activation times naturally follow a statistical distribution that arises from random environmental factors beyond the control of the warning system. The low end of the distribution must never be shorter than the mandated 20 seconds, but the long end of the distribution will inevitably have some outliers. The diagram above shows the measured distribution of 38255 crossing activation times on RTD. Notice the long tail.
     
  5. Even traditional "constant" warning time systems have this statistical tail. If the FRA inspectors applied the same regulatory zeal to Caltrain as they did to RTD, Caltrain would certainly be found in non-compliance. This isn't idle speculation: RTD gathered the data to prove it.
     
  6. The criteria for non-compliance, namely a "significant difference" from the prescribed warning time, are subjective. Guidance from the FRA acknowledges as much: "Thus, prudent judgment must be exercised when reviewing the results of warning time testing to determine whether the actual warning time provided during testing was compliant with the standard."
     
  7. The regulators painted themselves into a corner. They imposed a strict -5/+15 second criterion, which is easy to verify for an inspector with a stop watch and a clip board, but makes the long tail of the activation time distribution an automatic violation that is almost impossible to avoid. In recognition of the environmental factors beyond the control of the warning system, the regulators should have used controlled test conditions or applied a different criterion, such as X% of activations within Y% of programmed warning time. This is harder to verify for an inspector with a clipboard, but the grade crossing controller ought to be able to maintain these statistical records across a very large number of crossing activations.
     
  8. While electrification is relatively rare in the US, there are numerous railroads abroad that have solved the constant warning time problem in electrified territory. This probably isn't rocket science. The mousetrap already exists.
Lessons for Caltrain
With the grade crossing warning system already at the top of the Caltrain electrification project's risk list and the contractor falling behind, this problem is already getting a lot of attention. The people involved hopefully already realize:

Keep it simple - the job is to come up with a grade crossing predictor that works in the presence of traction return currents. It will be tempting to come up with a more sophisticated custom solution that uses lots of software, but we learned from the CBOSS project, and Denver's travails, that complexity usually leads straight to disaster. The dumber the better.
Document existing conditions - a large database of activation time statistics should be assembled for each crossing as it exists today, to head off a conflict over the subjective nature of the FRA warning time consistency criteria. In the event of a Denver-like disagreement with FRA or CPUC, Caltrain would be in a position to quantify precisely how much more (and hopefully not less) consistent the new warning solution will be, regardless of the selected criterion. Caltrain enjoys the advantage that it isn't building new crossings like Denver, so there is an existing system performance baseline that is already accepted by regulators. That baseline will only be useful if it is thoroughly documented.
Plant the goal posts firmly - Work with FRA towards mutually agreed verification criteria that don't repeat the mistakes made in Denver of specifying a rigid range and then testing in the uncontrolled conditions of revenue service. The activation time distribution will always have a statistical tail. If the consistency criterion can't be met by today's existing grade crossing system, then it's probably a bad criterion.
Make sure we aren't paying for Denver - the contractor needs to be held accountable for the extent to which Caltrain electrification funds (and schedule delays!) are accruing to the Denver project's benefit, if the same grade crossing solution is ultimately pursued in both projects.