05 April 2014

Saving Some Trees

One of the most controversial elements of the Caltrain electrification DEIR is the need for tree pruning or removal to establish adequate clearance between vegetation and the live parts of the overhead contact system, energized at 25,000 volts or more.  While the exact regulatory details governing 25 kV electrification are still being hammered out at the CPUC, vegetation clearances are likely to be governed by General Order 95, Rule 35, Appendix E, which states:
The radial clearances shown below are recommended minimum clearances that should be established, at time of trimming, between the vegetation and the energized conductors and associated live parts where practicable. Reasonable vegetation management practices may make it advantageous for the purposes of public safety or service reliability to obtain greater clearances than those listed below to ensure compliance until the next scheduled maintenance. Each utility may determine and apply additional appropriate clearances beyond clearances listed below, which take into consideration various factors, including: line operating voltage, length of span, line sag, planned maintenance cycles, location of vegetation within the span, species type, experience with particular species, vegetation growth rate and characteristics, vegetation management standards and best practices, local climate, elevation, fire risk, and vegetation trimming requirements that are applicable to State Responsibility Area lands pursuant to Public Resource Code Sections 4102 and 4293.
10-foot tree clearances, from DEIR
The CPUC rule establishes minimum clearance of 4 feet at the time of trimming, and gives Caltrain discretion to increase the clearance as needed.  Caltrain has added another 3 feet of allowance for wind sway, and another 3 feet on top of that for vegetation growth between trimmings.  This brings the overall clearance carried in Caltrain's DEIR to 10 feet, as shown in the diagram at right.

This 10-foot clearance drives the number of trees impacted by the project: 2,200 are due for removal and another 3,600 for pruning according to the DEIR.

Outside Poles

The standard configuration of the overhead contact system places poles on the outside of the tracks, near vegetation.  The clearances look like this:
This configuration tends to have the worst impact on vegetation, mostly because the 50 kV feeder wires attached to the tops of the poles are near vegetation all along the right-of-way, even in the long open spaces between poles (right-hand diagram).  This is the main reason why 2,200 trees face the chain saw.

Inside Poles

To keep high-voltage components away from vegetation, it is possible to locate the poles between the tracks in the middle of the right-of-way.  This requires slightly more space between the tracks; the regulatory minimum is approximately 18 feet (2x 8'3" minimum from track center line to pole face, plus the width of the pole itself, plus some error margin).  The diagram below shows 19-foot spacing, with taller poles to carry both feeders with adequate clearance from each other:
While this configuration spreads the tracks apart by four feet, the resulting impact to vegetation is less, especially between pole locations, because the feeders are kept away from vegetation.  The down side is that tracks need to be moved apart; this is not very difficult except where cross-overs are located.

Portals

Portal gantries are basically the same as side poles, with a cross-bar across the top.  Like center poles, the portal arrangement allows the 50 kV feeders to be located in the middle away from vegetation.  Unlike center poles, portals do not require the tracks to be further apart than 15 feet:
The portal configuration has the least impact on vegetation between poles (right-hand diagram) but isn't particularly beautiful (left-hand diagram).

Most of the 2,200 trees threatened by electrification probably aren't worth saving.  They are typically not "heritage" trees, and consist mostly of unremarkable species that have grown haphazardly into the right-of-way.  But there are surely certain trees worth saving, and for those, the support arrangement of the overhead contact system can be engineered to keep high-voltage feeders away from vegetation, over the tracks.

04 March 2014

CalMod Gains Momentum

CalMod is the corny abbreviation for the Caltrain Modernization program, which encompasses the CBOSS train control system and the peninsula corridor electrification project (PCEP, if you really want to sound like you're in the know).  CalMod is kicking into high gear this week, with the following major developments:
  • Release of the revised DEIR, a major step to clear the electrification project under CEQA.  Compared to the last edition of this document from 2009 (itself warmed over from 2004 and used to garner FTA approval of the project under NEPA), this update is a much stronger and more thorough document that clearly reflects the higher degree of public awareness of the project.  The JPB plans to certify the final EIR this fall.
     
  • At the next board meeting, award of a six-year $4.3 million contract to the new Director of Project Delivery, Dave Couch.  This is a name we'll see much more of in coming years, as Mr. Couch will take charge of orchestrating the day-to-day management of the army of consultants, staff and contractors that will expend $1.5 billion to deliver the modernization project.  It appears that he will report to Marian Lee (CalMod executive officer).
     
  • Also at the next board meeting, award of a six-year, $24.2 million contract to LTK Engineering Services to carry out the procurement and supervise the design, manufacture, delivery, testing, and entry into service of Caltrain's new fleet of Electric Multiple Unit (EMU) trains.  LTK has a long history of providing Caltrain's in-house vehicle expertise, and this contract expands their role.  At typical overhead burden rates, the budget looks like it will pay for about 8 to 10 full-time positions for the duration of the project.
It's full steam ahead, even if there remain significant obstacles.
  1. HSR bond funds.  The elephant in the room is the ongoing legal wrangling over the high-speed rail bond funding that makes up about half of the CalMod budget.  CalMod executive officer Marian Lee recently gave a surprisingly candid statement to a Daily News reporter:
    Asked if there's any danger of Caltrain not receiving the state money if the high-speed rail project is killed in the courts, Lee offered a pragmatic response.
    "We have to hurry up and spend the money, because if they disappear, they disappear with the money," she said. "Then we are half short."
    The question seems to be whether they will get any money at all, never mind spending it quickly.  This could be the number one show-stopper as lawyers prepare to debate the minutiae of trip times and compliance with the bond act.  If the HSR project folds, things may quickly become interesting.
     
  2. Piece-mealing challenge.  The DEIR is likely to draw a lawsuit that challenges the boundaries between the electrification project and the high-speed rail blended project, claiming that electrification is the camel's nose under the tent for HSR.  CEQA prohibits a practice known as "piece-mealing," whereby projects are analyzed incrementally by parts to make the environmental impacts appear smaller.  Caltrain would have to make the case in court, as it already does in the DEIR, that the electrification project stands separately on its own merits regardless of the source of funding.  CEQA is a self-enforcing statute, so lawsuits of one kind or another are expected.
     
  3. Regulatory teething issues.  A big question mark is the CPUC rule-making process for 25 kV electrification, which despite the world-wide ubiquity of this technology is nevertheless a first within the borders of California.  The CHSRA consultants have run away with the process by tailoring it far too narrowly to high-speed rail, which may create a problematic regulatory gap for Caltrain and delay the electrification project.
As is customary in 21st-century California, the process will be far more expensive, slow and litigious than in other first-world countries.  Par for the course.

11 February 2014

Draft Business Plan Impressions

The high-speed rail draft 2014 Business Plan is out, with some interesting implications for the peninsula corridor.

Example service plan, from the 2014
draft business plan supporting documents
New Emphasis on Regional Markets

The ridership model has been (somewhat) updated, although much more is supposed to come, and it's clear that there is now more emphasis on serving local markets.  This theoretically places the high-speed rail system in direct competition with Caltrain.


An example service plan, buried in the supporting documents, is shown at right.  The majority of early-morning trains are local commuter milk runs, including 4 trains per hour serving peninsula stops as well as 4 trains per hour from Palmdale to Los Angeles.

That's all well and good for starting up service in the morning, but one wonders how these customers are catered to during the evening rush (especially to Palmdale) when these commuter milk runs will have to co-mingle with long-distance express trains long before the midnight shut-down, unlike in the early morning when the milk runs coincide with the 6 AM startup.  Here on the peninsula, the speed differential between HSR and Caltrain will be far less, so this problem isn't as acute.

Realistic Peninsula Corridor Trip Times

The trip times embedded in the business plan and the underlying ridership calculations now appear consistent with what can be achieved in a Caltrain - HSR blended service pattern on the peninsula corridor.  These trip times are significantly longer than the 30-minute theoretical SF to SJ minimum that could be achieved under ideal conditions as demanded by the HSR bond measure.  While this shortfall is sure to be the subject of further litigation, it should not detract from the far more egregious loss of trip time due to poor routing choices in the southern part of the state.

The trip between San Francisco Transbay and San Jose is conservatively timetabled at 47 to 49 minutes including a two-minute stop in Millbrae, which is consistent with Caltrain's analysis of blended Caltrain / HSR operations assuming a maximum speed limit of 79 mph for all trains (the same as today).  This isn't too far off from today's Baby Bullet timetable, which includes three more stops than assumed for HSR and therefore takes an additional 9 minutes.

Unrealistically Low Peninsula Fares

The fare model used to estimate ridership and revenue within the SF Bay region is based on an extremely simplistic MTC model that sets the fare to $14.97 plus $0.1283 per mile (in 2013 dollars).  This results in one-way fares of $22 from SF to SJ or $22 from Gilroy to Redwood City.  Such intra-regional trips displace higher yielding long-distance trips, since each seat sold for SF-SJ is a seat that cannot be sold for SF-Los Angeles.  Under any realistic scenario, the HSR operator will manage yields and set a fare structure that discourages low-yield, short-distance trips.  Look no further than the Northeast Corridor for an illustrative example: for a trip from Stamford, CT to New York City (roughly similar in time and distance as SF to SJ), a seat on Amtrak's high-speed Acela Express typically costs well over $100 one way vs. $14.50 on Metro North commuter rail.

Using these ridiculously low fares, the ridership and revenue model for the year 2040 predicts 2.5 million annual HSR riders within the SF to Gilroy corridor, worth $51 million / year in revenue.  That's approximately one-sixth of Caltrain's ridership today, but about two-thirds of the fare revenue.  The model essentially predicts that HSR will poach a large portion of Caltrain's highest-yielding passengers.  Caltrain need not fear for their revenue, however, since the simplistic MTC fare model that underlies this result is not likely to be used by a real-world, for-profit HSR operator.

To Redwood City or Not to Redwood City

Most of the business plan assumes only three peninsula corridor stops for HSR: San Jose, Millbrae and San Francisco Transbay.  The ridership and revenue memorandum, however, includes Redwood City in a fare table.  Furthermore, some of the peninsula trip times in the service planning memorandum are timetabled at 49 minutes (see example service plan, page 8, making sure to account for arrival vs. departure times), which is consistent with an additional stop at Redwood City.  The 33-minute trip time indicated between SJ and Millbrae is very conservative and could easily be timetabled at 29 minutes (departure to arrival) with a 79 mph speed limit and including two minutes of timetable padding.  The extra stop in Redwood City would bring it up to 33 minutes.  Coincidence?

13 January 2014

The Dual Mode Locomotive, Elephant of the Rails

Caltrain's revised DEIR for the electrification project is about to be released for public comment.  Meanwhile, California's high-speed rail project has suffered legal setbacks that may end up threatening a $600 million contribution of Proposition 1A HSR funds promised for Caltrain electrification  (the so-called "book-end" funding).  These events have awakened a small but vocal and persistent minority of peninsula residents who believe Caltrain should not electrify, and should seek alternate short-term solutions.

We've seen this pattern before: there was a lot of misinformation circulating about hybrid DMU trains, which were seen as an alternative to electrification when in fact they do not exist and are not capable of meeting Caltrain's requirement for high-capacity, high-acceleration rolling stock.

ALP45-DP locomotive
The new idea now going around at least has the merit of being demonstrated in the real world.  The idea is to replace Caltrain's locomotive fleet with a new type of locomotive known as a dual-mode locomotive.  You can think of it as two locomotives in one, combining a conventional diesel power train with the ability to operate on electricity where 25 kV overhead electrification is available.  To pull off this feat, the locomotive needs to carry not only a diesel power plant and an electric generator, but also a big transformer to bring the 25,000 volt electric supply down to usable voltages.

There is an off-the-shelf example: Bombardier's ALP-45DP, shown in the photo at right.  A small fleet of these beasts operates for commuter agencies in New Jersey and MontrĂ©al, Canada, where certain lines are only partially electrified.  Rather than inconveniencing passengers with a change of trains where the wire ends, these locomotives fire up a pair of 2,000 horsepower V-12 engines and continue their trip beyond electrified territory.

These make absolutely no sense for Caltrain.
  • They are expensive.  Two locomotives in one cost almost as much as two locomotives.  New Jersey Transit paid $8 million for each one in 2010.  Caltrain would require a fleet of about 25.  There goes $200 million, nearly half the amount allocated to the new fleet purchase under the electrification project, and none of Caltrain's aging passenger coaches would be replaced.
     
  • They are heavy.  These locomotives have the heaviest axle load of any passenger locomotive in the world, at nearly 33 metric tons.  Heavy beats up the track and increases maintenance costs.
     
  • They are slow in diesel mode.  Even with two 2,000 hp V-12 engines pulling as hard as they can, the million-pound weight of a Caltrain commuter train will hold the train back and limit the trip-time savings of an all-stops peninsula local to just one minute, all else being equal.
     
  • They are slow in electric mode.  Imagine that some day the funding finally comes together to string up electric wire along the entire length of the peninsula.  The laws of physics being what they are, the power-to-weight ratio and the weight on drivers of a train powered by a dual-mode locomotive does not allow it to accelerate quickly, even if its rated top speed is 100 mph.  In stop-and-go service on a local train, an ALP-45DP running in 100% electric mode would only save four minutes on its entire run between San Francisco and San Jose, compared to today's timetable.
The trip time savings simply aren't worth the high cost of dual-mode locomotives.  Level boarding by itself (even with diesel locomotives) would save more time.  The lightweight and powerful EMU trains that Caltrain plans to purchase would save far more time, and are unbeatable when combined with level boarding.  See chart at left.

The only remote opportunity that dual-mode locomotives might present is the ability to serve the Transbay Transit Center, which is not designed for diesel trains, prior to the full electrification of the peninsula corridor.  The San Francisco downtown extension tunnel, however, won't be completed for at least another decade and will cost two to three times more than Caltrain electrification.  That's an awfully long time to realize the meager benefits of dual-mode locomotives, on a shaky premise that funding won't be available for Caltrain electrification even after the DTX is paid for in full.

For the peninsula rail corridor, dual-mode locomotives are clearly a proven solution looking for a problem.  The better problem to solve is how to fund the electrification project even if the high-speed rail funding is denied.

11 January 2014

The Canyonero of Signals

The San Bruno grade separation, a $155 million project that does nothing for the average Caltrain rider, is nearing completion.  If you wondered where some of that money went, here you go.

The Canyonero of signals is surely this brawny Made in U.S.A. signal gantry mounted on top of the San Bruno grade separation.  The gantry (probably a standard two-track gantry, to save money!) was too wide to be mounted in this location, so two cantilevered concrete platforms, seismically worthy, were built on each side to support the gantry and keep out any terrorists.  [UPDATE: check out the engineering drawing!]  If that wasn't enough, this signal gantry needed its signal house (probably a standard 8'x8' signal house, to save money!) perched on top of the opulent platform as well, with classy electrical conduits slung underneath and a dedicated ADA-compliant staircase allowing maintenance personnel ready access.  Maybe they were trying to save some parking spaces by suspending everything, but the entire area had to be fenced in for security.
East side, showing cantilever platform West side, with signal house on cantilever platform Under-hanging conduits connecting the signal heads to the relay shelter
If you asked the engineers who designed this, they could no doubt bend your ear about why it ended up this way and how numerous standards and requirements conspired to force exactly this solution.  That doesn't remove the simple fact that it's wrong.  It isn't simple, elegant, efficient, or thrifty; it fails to satisfy basic ideals that all engineering has aspired to since time immemorial.  The ridiculous, over-wrought outcome of rigid paint-by-numbers adherence to prescriptive requirements and standards would be comical if it weren't such a waste of the scarce taxpayer dollars available for rail projects.  (Or even that sub-category of rail projects solely benefiting automobile traffic flow.)  It's a basic signal gantry, for crying out loud.

Oh, and the new speed limit at the San Bruno curve, the #1 worst curve on the entire peninsula?  65 mph, up from 60 mph before.  It could have been 100 mph if this project had been conceived intelligently.

The concrete has been poured, and this installation shall now and forever stand as a monument to our Transit Industrial Complex, as it embarks on far more challenging endeavors such as electrification, level boarding, the downtown extension, and maybe some day high-speed rail.  The symbolism is hard to avoid.