| Welded aluminum shell of a cab car | Front cab shell at right | Intermediate car, after paint |
Maybe if those trade sanctions kick in, they won't have anywhere to go?
The passage of California Proposition 1A (2008) set in motion a complete reconstruction of the railroad between San Jose and San Francisco. This blog exists to discuss compatibility between HSR and Caltrain, integration issues, and the impact on adjoining communities.
![]() | ![]() | ![]() |
| Welded aluminum shell of a cab car | Front cab shell at right | Intermediate car, after paint |
Blended System issues. Access to San Francisco’s Transbay Terminal has posed a challenge to the program from the beginning. The ideal engineering outcome – a new, four track system separating HSR from Caltrain and freight service – was problematic because of its high cost and environmental impact. An alternative approach was adopted that blends the services of Caltrain and HSR on the same two track system, mostly within the existing right-of-way but with specific additions of passing tracks where needed and with the possibility of incremental increases in capacity when justified by demand. When combined with electrification of the Caltrain lines, paid half-and-half by Caltrain and HSRA, this approach should work to serve the needs of both systems at least through the first decades of the Phase I Blended system. In a number of our previous letters, the Group has supported the blended system approach; our comments below are aimed at improving its implementation.The Peer Review Group's comments are a wake-up call to start breaking out of the silo mentality that is prevalent in our transportation agencies, where "staying the course" is too often the overriding consideration. The blend can only succeed if all stakeholders adjust their plans and projects to achieve better coordination and system-level integration. The Peer Review Group understands that we are at a juncture where this opportunity must not be squandered.
The blended approach will require a true joint effort by Caltrain and HSRA with full participation of other parties including the Transbay Joint Powers Authority (that has the responsibility for the connection from the current Caltrain terminus at 4th and King Streets to the Transbay Terminal) and the Union Pacific Railroad (that has freight operating rights on the same lines). There are a number of issues on which the interests of the parties must be explicitly balanced if the blending is to work:
None of these problems is impossible to resolve, albeit at added investment and operating cost by one or more of the parties. There is nothing unique about having multiple freight and passenger operators on a single line and there is experience in the U.S. and Europe with resolving the normal issues. All parties in the blended area are aware of the issues and there has been full cooperation among them.
- Currently, Caltrain uses a platform height of 8” above rail. This means that boarding/de-boarding requires stepping up/down from the floor of the train (25” above rail), which can impose delays and risks of tripping and falling, especially when the needs of disabled passengers must be accommodated. The result is longer and less reliable schedules. The low platform height is dictated by the regulations of the California Public Utilities Commission (PUC) that require platforms to be no higher than 8” on tracks that may also carry freight trains. Unless a waiver from this regulation is granted, or expensive track work is installed, Caltrain will be limited to low platforms. At its current frequency of services, the lack of level boarding is manageable (if undesirable), but it will become much less tenable when Caltrain frequencies are increased and HSR trains are added.
- Under current plans, the floor of HSR trains will be about 50” above the rails, which is typical practice for most of the world’s HSR systems and consistent with Amtrak’s plans in the Northeast Corridor. Caltrain is experiencing rapid demand growth, a process that will accelerate when service to the Transbay Terminal is inaugurated. Caltrain’s plans call for acquiring new bi-level, electric multiple-unit rolling stock. Since the existing Caltrain coaches have a 25” floor level, consistency would suggest a 25” floor level for the new equipment. This would mean that platforms for the two systems would be at different levels, making transfers within station more difficult to arrange. This might be manageable at many common stations where Caltrain and HSR could have separate platforms, but the platform disparity would be more serious at the Transbay Terminal because the number of platforms is limited. As a result, routing of traffic into and out of the station will be more complex, and dispatchers will not have the flexibility to send either system to all platforms when delays or operating problems would otherwise dictate. One approach, turning a number of Caltrain services at 4th and King and limiting the number of Caltrain services to the Transbay Terminal, has been suggested, but would pose restrictions for Caltrain’s access to the Transbay Terminal.
- The basic standards of the PUC for electric catenary wire call for a clearance of 22 feet 6 inches above the rail. One the one hand, both Caltrain and HSR may want a lower catenary height in order to reduce construction cost for which the PUC will have to grant permission: on the other hand, the Union Pacific and port interests may want to protect the hypothetical possibility of future freight cars requiring even more clearance. HSR’s current electrification designs are appropriate for HSR-only operations and may not be acceptable for use in the Caltrain area. There are a number of specific locations where Caltrains’s clearance is already below 22 feet 6 inches, but there is no generally agreed height limitation.
- Positive Train Control (PTC) is a requirement of Federal law. Facing this mandate, Caltrain developed its own system – CBOSS – that is now being implemented. CBOSS may not be appropriate for use by HSR trains. If so, HSR trains may have to deal with two signal systems. In addition, the Union Pacific Railroad will have to operate in the same territory so will have to have conforming signal systems in its locomotives.
We are concerned, however, that near-term decisions could be made by the parties acting separately that would ultimately compromise the performance of the system. For example, a decision by Caltrain not to plan for at least 25” platforms, which would provide an essential approach to level boarding, would lead to increased delays and uncertainty that could become unmanageable when Caltrain frequencies increase to meet the rapidly growing demand, especially that caused by the opening of the Transbay Terminal. This problem would get worse when four HSR trains per hour are added to the blended system in 2026. Caltrain will definitely need an expanded fleet, and bi-level cars are an efficient way to meet the need. That said, a decision to buy 25” floor level, bi-level coaches would mean that Caltrain and HSR would be committed to operating on incompatible platforms, which would add rigidity to a system that will be challenged for capacity. This problem could be alleviated if Caltrain ordered coaches that can serve both platform levels or if it adopted a uniform 50” platform, but either solution would clearly add investment costs above those planned. In all cases, the design of the electrification for Caltrain will need PUC approval and will need to consider the interests of all of the operators on the line.
This is a complex issue involving technology, investment, system performance and sequencing including the interests of a number of parties. Clearly there is no perfect answer and it is actually a problem resulting from success in attracting more passengers. We recommend that the Legislature request periodic joint reports from Caltrain, HSR and the Union Pacific Railroad that will use the tools available, including line capacity simulators, to assess the impact of alternative approaches to coach floor and platform height on capital and operating cost, capacity and reliability of both systems. This would include the impact on Caltrain if it has to construct 25” or 50” platforms. This study should also include the investment and operating cost impact of the alternative approaches to catenary height and platform clearance and should outline the decisions that the PUC will be asked to make.
Blended operations also pose the issue of accidents at grade crossings. Even at its existing speeds and frequencies, Caltrain experiences about 20 grade crossing and intruder deaths per year and generates delays on the local streets as autos and trucks wait for passing trains. This will get worse as train frequency and road traffic both increase over time. It would be difficult to overstate the risks of more frequent, faster and quieter Caltrain service combined with 110 mph HSR trains interacting with growing road traffic in the middle of California’s increasingly busy cities. We recommend that the Legislature ask Caltrain, HSR and the communities involved to develop a joint report assessing the likely future risks of increasing train traffic and speeds on the grade crossings in the areas impacted and identifying possible approaches to resolving the issue over time.
The radial clearances shown below are recommended minimum clearances that should be established, at time of trimming, between the vegetation and the energized conductors and associated live parts where practicable. Reasonable vegetation management practices may make it advantageous for the purposes of public safety or service reliability to obtain greater clearances than those listed below to ensure compliance until the next scheduled maintenance. Each utility may determine and apply additional appropriate clearances beyond clearances listed below, which take into consideration various factors, including: line operating voltage, length of span, line sag, planned maintenance cycles, location of vegetation within the span, species type, experience with particular species, vegetation growth rate and characteristics, vegetation management standards and best practices, local climate, elevation, fire risk, and vegetation trimming requirements that are applicable to State Responsibility Area lands pursuant to Public Resource Code Sections 4102 and 4293.
![]() |
| 10-foot tree clearances, from DEIR |
Asked if there's any danger of Caltrain not receiving the state money if the high-speed rail project is killed in the courts, Lee offered a pragmatic response.The question seems to be whether they will get any money at all, never mind spending it quickly. This could be the number one show-stopper as lawyers prepare to debate the minutiae of trip times and compliance with the bond act. If the HSR project folds, things may quickly become interesting.
"We have to hurry up and spend the money, because if they disappear, they disappear with the money," she said. "Then we are half short."
![]() |
| Example service plan, from the 2014 draft business plan supporting documents |