The Original Plan
To maximize the short-term seating capacity of the new trains until the 2030s, Caltrain specified that the intermediate level should have temporary flip-up seats installed in front of the unused doors, five per door vestibule, with the seating blocking off the doors like this:
Configuration of intermediate level in A, B, C, E, and G cars |
At some undetermined future date when the intermediate doors would be needed for compatibility with high platforms, the blue flip-up seating modules would be removed from the intermediate level.
A Regulatory Conundrum
In the design of any new train, federal safety regulations require that any passenger seating compartment be fitted with at least two emergency exit windows (for passenger egress) and two rescue access windows (for first responder ingress). The intermediate level counts as a passenger compartment because these flip-up seats are located within it. However, the intermediate level does not have what regulations consider to be a window; the only opening to the outside is through the doors. This set up a conflict with safety regulations.
In late 2017, Caltrain petitioned the Federal Railroad Administration for a waiver (docket FRA-2018-0003) by arguing that the emergency release feature of the doors would provide an equivalent level of safety, despite not meeting the letter of the regulation, allowing emergency access by climbing over the seat backs.
In June 2018, the FRA denied Caltrain's request because the flip-up seating installed longitudinally such that it blocks the doors could impede egress and access and therefore did not meet the intent of the regulation. The FRA stated that "the absence of need for these intermediate level doors to support current revenue boarding and alighting requirements does not negate the necessity for an unobstructed path in the event of an emergency." Curiously, this unobstructed path requirement applies only to doors, not to windows!
Implicitly, Solution A is to remove all seating from the intermediate level of the affected cars, which effectively sidesteps the emergency window requirement. But given that seating in Caltrain's EMUs is already quite limited, this solution seems like a non-starter as it would reduce seating capacity of a 7-car train by 9% from 667 seats to just 617 seats.
Solution A: not a passenger seating compartment |
Solution B: equip the intermediate level doors with a regulation-size emergency window of minimum dimensions 26" wide by 24" high. Unfortunately, that is too large for the dual-leaf design of the train doors; in other words, the window in each door leaf is too narrow to function as an emergency window.
Solution B: the minimum clear opening is too big for dual-leaf doors |
Solution C: doors replaced by plug panels |
Other Solutions
There are other solutions that strike a better balance of functionality and simplicity without a seven-figure cost impact.
Solution D: short of removing all the seating from the intermediate level vestibule, the regulations require only one emergency window (instead of two) if there are four or fewer seats in the compartment. Removing seats from one side only and applying for a new waiver to allow unobstructed use of one of the doors in lieu of a single emergency window could work, addressing the FRA's stated concern with door obstruction. This would reduce seating capacity of a 7-car train by just 22 seats or 3% (5 seats lost in cars A and B, and 4 seats lost in cars C, E and G).
Solution D: reduced seating with unobstructed emergency access |
Solution E: change flip-up seating orientation to provide unobstructed door access (flip-up seats are shown in use; they fold flush against wall when not occupied) |
Flip-up seats in a doorway of a brand new Bombardier EMU on Paris RER line D. (foreground at left) credit: Wikipedia / KiHa 52 |
Ultimately, it is entirely possible that Caltrain simply does not wish to interface with high-speed rail in any station as a matter of policy, because it would require sharing and collaborating with another agency, and solving a somewhat complicated ADA compliance problem. Which agency would voluntarily bring that upon itself? Caltrain already took the HSR money, and installing plugs will "erase" the clunky and unpalatable concession they made in the name of compatibility, with the further bonus of not requiring another run at the FRA for a new waiver. The complicated ADA compliance issues associated with interior lifts are kicked as far down the road as possible!
No matter how you look at it, Caltrain's chosen approach is a ~$15 million mistake that reduces and complicates compatibility with HSR stations and platforms. There are cheaper, simpler and easier ways to achieve compliance with emergency window regulations. It's not too late to change course.
"Ultimately, it is entirely possible that Caltrain simply does not wish to interface with high-speed rail in any station as a matter of policy, because it would require sharing and collaborating with another agency, and solving a somewhat complicated ADA compliance problem. Which agency would voluntarily bring that upon itself?"
ReplyDeleteCkem, in your assessment does this mean that Caltrain has given up on level boarding entirely? Allegedly this was supposed to be part of the business plan.
I think for a long time there wasn't complete agreement on the value of level boarding, nor how to go about implementing it. They didn't have the bandwidth to think about it thoroughly. The business plan effort is changing this gradually. They do have a very strong preference for doing level boarding at 550 mm (lower level) which is why the high doors are so unpopular.
DeleteCall my cynic, but I'd much rather see $15 mistakes that still leave us with workable system than the PTC debacles.
ReplyDeleteSolution D is probably playing on a technicality. The idea of windows on both sides is in case the train falls on its side. I might be work, but I'd guess the exception for just 1 window is probably applied only to trains with compartments on one side and hallway on the other side.
I like your solution E - although I realize, it's something done elsewhere. Which brings up a point of why Stadler didn't propose such a solution to Caltrain. After all, they would understand the needs for evacuations and have some experience with regulations around the world - some of which would drive that solution.
Who said that this was Caltrain's problem to solve???
ReplyDeletehttps://www.era.europa.eu/sites/default/files/library/docs/opinion-advice/opinion_era-opi-2015-10_en.pdf
Very nice summary of a complex subject, although the policy goals may differ. For example, page 9, "Unassisted boarding is not at the moment an explicit objective in either the RSSB's platform-train interface strategy or the TSI's." Unassisted boarding needs to be an explicit objective here: dwell time roulette is not a game you play on a corridor as busy as Caltrain will eventually become.
DeleteHere you go: https://ec.europa.eu/transport/modes/rail/interoperability/interoperability/prm-tsi_en
DeleteYou clearly outdid yourself this time:
ReplyDelete1) You posted a picture or a Regio 2N CAB CAR instead of one of the single-level traction power units
2) Please provide a picture of a Regio 2N BI-LEVEL PASSENGER CAR "with electrical cabinets (labeled with yellow lightning bolts)". Clue: you won't because all the electrical equipment is located either above the ceiling or below the floor of the single-level traction power units
I fail to see how the "CAB CAR" has different flip-up seats than the other cars, but here's another photo to illustrate my point that there are seats placed in front of all the doors, on a Parisian train that serves traffic densities that Caltrain can only dream of.
DeleteRegarding electrical equipment: it's apples and oranges. If you want the same anemic acceleration performance as a Regio 2N, you can delete a bunch of electrical equipment in the Stadler EMU by simply changing the consist. Delete power car E (-100 seats), add unpowered all-seating car H (+132 seats), and remove all traction equipment from cab cars (+8 seats each). That's +48 seats just from deleting the extra-performance cabinets.
Now get rid of half the bike space (minus one bike car, +43 seats), add five-abreast seating (+86 seats upstairs, +16 intermediate level, +56 downstairs; yes the Stadler is wider than the Regio 2N), and add 6 Paris-style strapontins to each lower door vestibule (+96 seats)
Just by playing with the interior layout to make it more like your Regio 2N, I've increased the 8-car Stadler EMU from a seating capacity of 799 (baseline) to a monstrous 1144 seats. Using only a pencil, I jacked up the seating density by 43% to a generous 5.5 seats/meter of train length. It doesn't take a PHD (Porteur Hyperdense) to pack in that many seats.
For years you had this mistaken for a Bombardier vs. Stadler issue, but all along it was just a sad little matter of interior layout choices.
"Au total, 520 places assises fixes et 62 strapontins sont proposés dans une rame de 110 m. Les trains d'hyperpointe seront assurés en UM3, avec une capacité assise totale de 1746 places"
DeleteAre we having fun yet?
Here is a wonderful table showing:
Delete- "Seated capacity incl. tip-up 2+2 / 2+3 seating"
- "Number of toilets (incl. 1 for wheelchair user)"
https://www.bombardier.com/content/dam/Websites/bombardiercom/Events/Supporting%20Documents/BT/bombardier-transportation-OMNEO-brochure-en.pdf (page 9)
Enjoy!!!
What I'm really enjoying right now is that you haven't yet bothered to divide the 1144-seat capacity of my Stadler EMU-8 (with interior layout suitably reconfigured for maximum seating capacity) by its length of 209.8 m, and compared the resulting linear seating density to the same metric for your Regio 2N. Try it.
DeleteIf you did that simple division, you would prove my point that seating density is a matter of interior layout choices.
Again, the four key factors are:
- lower performance --> more compact traction equipment
- five-abreast seating
- flip-up seating in all doorways
- limited bike space
None of those factors are intrinsic to one train or another! Caltrain chose to configure its EMU with:
- very high performance (BART-like!)
- four-abreast seating
- lower-deck vestibules without seats
- tons of bike space, relative to world standard practice
Pining for a different brand of train won't change that. It's like Boeing versus Airbus arguments when the entire difference comes down to airline-specific interior configuration choices.
What I am really enjoying right now is that you also (deliberately?) missed the "Power at rail (MW)" which shows 6.4 MW for a 216.4 M train without a single "electrical cabinet (labeled with yellow lightning bolts)" in sight. 8 MW is there for the asking by people who are not responsible for energy bills.
DeleteRe "anemic acceleration":
ReplyDelete"Côté performances, l'essai n'est pas totalement représentatif, car on se hâte avec lenteur sur la rive droite. Avec une accélération à 0,6 m/s², le Régio2N en version 110 m et 3 bogies moteurs n'est certes pas un foudre de guerre, mais c'est - un peu - mieux que la Z5600 6 caisses qui plafonne à 0,53 m/s². Dommage que le STIF n'ait pas privilégié une version à 4 bogies moteurs qui aurait permis de monter à environ 0,75 m/s²."
Starting acceleration (limited by tractive effort) is one thing, yes. Sustaining that acceleration to higher speeds (limited by power) is another, and also determines how quickly you reach full speed. The metrics you quote don't tell the full story; the Regio 2N has low power (in round numbers, 2.4 MW for a 100 m train; Caltrain is 8 MW for a 200 m train).
DeleteHelp me understand something. Let's pretend it's 2030, and Caltrain trains are serving some some number of high-speed rail stations that have higher ("intermediate") level boarding. A person that can't do stairs will be able to ENTER a Caltrain train at one of those stations, using the higher doors - but where's that person going to RIDE, if there are no seats anywhere on that level, or anyplace a wheelchair can stay?
ReplyDeleteThere would be an interior lift inside each car, rated for 800 lb, to reach the lower level. Initially, Caltrain is only installing two lifts per train, between the bathroom car (C car) and the adjacent cab car (B car).
DeleteOT and ABSOLUTELY H-I-L-A-R-I-O-U-S
ReplyDeletehttps://www.hsr.ca.gov/docs/programs/track/Part_B-2-2-1_TS1_2-1-Systemwide_Alignment_Schematic-2019-0501.pdf
It takes real effort to do Every Single Thing Wrong and do it Every Single Time.
DeleteThere is nothing -- nothing -- in this schematic that makes the slightest operational or economic sense.
Death is too kind a fate for these ignorant, incompetent, rent-seeking, hostile, and limitlessly stupid sub-cretins.
Wait until you find out where this came from: yes, ladies and gentlemen, Diridon, 4th & King & Gilroy (and everything in between) are 100 % ready for design/build contracts!!!
Deletehttps://www.hsr.ca.gov/business/contractors/track_and_systems.aspx
FYI ---
ReplyDeleteI can't read the article in today's LA Times (behind the paywall), but the headline is:
In A Blow To The Bullet Train, California Might Shift Billions To L.A. And Bay Area Projects
https://www.latimes.com/california/story/2019-07-28/california-redirects-funds-high-speed-rail-project
From what I could glimpse, improving MetroRail between Anaheim to Burbank, improving Interstate 5, and improving Caltrain to SF, would be made the top priorities [the Summer Olympics will be in LA in 2028].
I don't see how it impedes or prevents CHSRA's goals though, so long as Pacheco is financed. Metrolink needs their own track to make reliable service plausible, at least from Burbank to LA Union Station. This will require at least two new tracks and five station rebuilds (including LAUS run-through tracks), if not 3-4 tracks if turnouts at stations prove implausible. If construction began in '23, Metrolink would be ready for express trains by '27 about when construction for Mojave tunnels would occur. CHSRA might even be able to add a surcharge onto Metrolink and Surfliner tickets, giving them revenue.
DeleteThe danger isn't so much rebuilding Metrolink as it is getting CHSRA involved in the mess that has become the Caltrain DTX/2nd TBT. SF has shown it can screw things up much worse than LA.
Read the article without the pay-wall at:
Deletehttps://www.omaha.com/news/nation/in-a-blow-to-the-bullet-train-california-might-shift/article_82d8c557-b509-5f56-9f8f-0bfa899223fd.html
( also you might turn off private viewing, which should allow direct viewing on the LA Times site (BTW, this was the Front page of the Times today 7-30-2019)
Airtalk Radio had Vartabedian in a discussion of his article, along with 2 other guests. This can be heard at: 32 minutes
https://drive.google.com/file/d/1wle67jgdxofKsp5FZN2Y0ndl1NVO1r7k/view?usp=sharing
Airtalk is hoping to have Brian Kelly on the radio tomorrow.
I think some Prop 1a issues will block a Burbank to LA Union transfer of funds. To list a few prop1 requirements:
Delete(2) the need to test and certify trains operating at speeds of 220 miles per hour
2704.09. The high-speed train system to be constructed pursuant to this
chapter shall be designed to achieve the following characteristics:
(a) Electric trains that are capable of sustained maximum revenue operating
speeds of no less than 200 miles per hour.
(3) Eighty percent (seven hundred sixty million dollars ($760,000,000)) of
the amount authorized by this section shall be allocated upon appropriation as
set forth in this section to eligible recipients, except intercity rail, as described
in subdivision.
I think SoCal needs to come up with a plan first before they start spending monies. Caltrains had their electrification plan ions ago and waited for eternity, it seemed like, before they got full funding.
If you believe (and I don't), Ara Najarian. who was on the Airtalk program cited about, Metrolink has shovel ready projects to use any and all funds directed their way.
DeleteStarting soon will be the money war between the south, the north and the CV,all trying to spend any funds available. The big loser is sure to be the CV.
My biggest fear is that if they don't finish what they started in the Valley the Valley will never get finished. California will end up with a California System North and a California System South and the Prop 1A requirements of SF-LA will get lost ad infinitum. Maybe not a bad thing but not what the voters approved.
ReplyDeleteCalifornia will end up with a California System North and a California System South system that beats the Prop 1A requirements of SF-LA by 10-20 minutes the day it forgets about the Pacheco and Mojave tunnels.
Deletehttps://www.scpr.org/programs/airtalk/2019/07/30/64734/local-groups-ready-rail-plans-as-california-consid/
DeleteYes, but regardless of routes, Merced and Bakersfield will be included. They don't build to them now, they will never have tracks.
DeleteYou don't understand... Merced and Bakersfield are on a FEEDER line (REAL high speed lines avoid cities like the plague!)
DeleteOh and BTW, what is your plan for Paso Robles and the CrossValley link?
I couldn't agree more that towns like Merced should be bypassed. I believe Merced is listed as a station in Prop1 though. Bakersfield isn't a bad stop for HSR. France has several cities along its HSR routes with lesser populations.
DeleteThis comment has been removed by the author.
DeleteHere is the end of the Paris-Bordeaux high speed line (LGV SEA):
DeleteSatellite:https://www.google.com/maps/place/Bordeaux,+France/@44.9306735,-0.4926111,304m/data=!3m1!1e3!4m5!3m4!1s0xd5527e8f751ca81:0x796386037b397a89!8m2!3d44.837789!4d-0.57918
Flyover: https://youtu.be/3BIF7j9DJvU?t=1782
Any questions?
Questions to what? A map?
Deletehttp://diamant-ltd.com/france-train-map-tgv/france-hsr-update-inspirational-france-train-map-tgv/
DeleteMany French towns smaller than Bakersfield have or will have HSR before it ever gets built to Bakersfield.
Let's try again (Poitiers)...
Delete1) Raccordement Poitiers Nord: https://youtu.be/3BIF7j9DJvU?t=520
2) Raccordement de Fontaine-Le-Comte: https://youtu.be/3BIF7j9DJvU?t=659
Ok, I think I got it. You have a fetish for French HSR videos?
Delete3 French Bakersfields ordering new trains due to high demand:
Deletehttps://www.francetvinfo.fr/economie/transports/sncf/sncf-la-commande-surprise-de-l-ete_3559315.html
http://worldpopulationreview.com/countries/france-population/cities/
Kindly help me understand which part of "high speed lines avoid cities like the plague" it is that you do not understand.
Deletehttps://www.tunneltalk.com/images/article-1187/image3.jpg
Deleteyes, but Europe is a far cry from the density and cost to acquire urban land then the US.
DeleteDensities:
Bakerfield: 2,543 sq mi
Birmingham: 11,000 sq mi
For discussions of statewide California HSR network design and construction phasing, may I suggest Altamont Press or Trainorders? Not here, please.
DeleteThe high level doors are never going to be used.
ReplyDeleteThe concept was moronic. Worse than moronic, because it gave the grifters and scammers and rent-seekers and non-achievers who bleed us dry while never delivering any service yet another out to promise to consider thinking about preliminary conceptual frameworks for studying alternatives to level boarding mañana mañana mañana mañana.
"High level" level boarding is stupid.
High speed rail isn't coming to San Francisco any time, and certainly not within the service lifetime of these too-narrow, far-too-little-revenue-space, far-too-little-roof-mounted-equipment, far-too-few-seats far-far-far-far-far-far-far-far-far-too-expensive far-too-few-sets trains.
Just stop it. Give up. Five-abreast single-level low-floor was what should have been ordered, and delivered and in service a decade ago.
Death is too kind a fate for anybody in any way connected with LTK Engineering Services, or any of the other millions-per-car grifters (not Stadler -- they're just happy to take idiot's money, good for them) who have dumped this pile of crap upon us.
It's awkward and clunky, yes, but it responded logically and self-consistently to a set of regulatory constraints in a way that made sense, before the concept got undermined and watered down. High level boarding isn't inherently stupid, or the entire Paris RER is stupid too, which I'm fairly certain isn't the case.
DeleteYes they could have specified wider car bodies to make more comfortable five-abreast seating, but bear in mind the Caltrain Stadler is wider than the 5-abreast Omneo, so again the same point I've been making to Roland is valid here: the low seating capacity of the Caltrain Stadler is purely a matter of Caltrain's interior configuration choices. Not body width, not roof-mounted-this-or-that, etc. Those are red herrings.
The question should always be how you move forward today-- coulda-shoulda-wouldas and undoing the past is simply not a viable option. I know it's hard to let go, I struggle with it myself, but pining for a different reality is just pissing into the wind.
"Bear in mind the Caltrain Stadler is wider than the 5-abreast Omneo".
ReplyDeleteDo you know how to read English or do you habitually make up useless shit for your lapping groupies?
"Pining for a different reality is just pissing into the wind."
Just like the I-ITCS CBOSS fiasco switch to Wabtec's I-ETMS, right?
No I don't know how to read English, but I do know how to read metric.
DeleteBombardier Omneo double-deck car shells are 2.99 m wide
Caltrain Stadler car shells are 3.00 m wide
"Width of single deck vehicles (m) 3.05"
Deletehttps://www.bombardier.com/content/dam/Websites/bombardiercom/Events/Supporting%20Documents/BT/bombardier-transportation-OMNEO-brochure-en.pdf (page 9)
The single deck vehicles do not contain 5-abreast seating (as confirmed by your brochure) and their width is therefore irrelevant to a comparison of which train (Stadler or Bombardier) is more suitable for the purpose of 5-abreast seating. 3.05 meters is neither here nor there. The brochure shows that the only vehicles with 5-abreast seating in the Omneo are double-deck sections with an exterior width of 2.99 meters. My statement that the Stadler is wider than the 5-abreast Omneo is factually correct.
DeleteAgain, with feeling: the low seating capacity of the Caltrain Stadler is purely a matter of Caltrain's interior configuration choices.
"A full second class OMNEO train with a 2+2 seating arrangement achieves an impressive ratio of 5 seats per
Deletemeter of train with seat spacing of 825 mm between unidirectional seat rows and 1,750 mm between face to face
rows. A 2+3 seating arrangement can increase this ratio to 5.8 seats per meter of train."
The interior layout based on rail mounted seats makes it easy to change from a 2+2 to a 2+3 seating arrangement
during the life of the train in order to meet increasing capacity needs.
https://www.bombardier.com/content/dam/Websites/bombardiercom/Events/Supporting%20Documents/BT/bombardier-transportation-OMNEO-brochure-en.pdf (page 9)
That's some nice salesmanship, thank you.
DeleteAs shown above, the Stadler could easily do 5.4 seats per meter of train if you chose a different interior configuration. Nothing warrants changing vendors or changing train architecture, let alone getting the Franco-French Bombardier Crespin factory to comply with Buy America regulations. If you're upset that the Stadler EMUs have too few seats, then your issue is with interior configuration choices made by Caltrain and their consultants, choices that have little to nothing to do with the choice of train vendor.
Caltrain could have bought a Stadler "hyperdense" but didn't. What part of this is so difficult to understand?
1) Unless I missed it, what is your solution for "EMU cars filled with electrical cabinets (labeled with yellow lightning bolts), with reduced capacity compared to a conventional train" (copy Bombardier or???). Are you saying that this crappy interior design is Caltrain's fault???
Delete2) Now that your stupid sets of doors at random heights are dead (and soon to be buried), how about resetting a level playing field and issuing an RFI to companies with a proven track record of designing and manufacturing hundreds of high SEATED capacity trains?
3) How about following BART's example and creating hundreds of good BAY AREA Buy America-compliant jobs in Pittsburg, CA (https://sf.streetsblog.org/2019/06/14/bart-train-plant-moving-to-pittsburg/) instead of pissing away hundreds of millions of OUR tax dollars on a new ASSEMBLY facility in Salt Lake City, UT?
You do realize that you can't force a company to build locally if you have to comply with Buy America, right?
DeleteAlso, why you think that Caltrain would cancel an existing contract with a vendor and reissue an RFP (when no other vendor responded to the original RFP) is beyond me. Bombardier had a beautiful opportunity to propose the OMNEO, they didn't. Same goes for Siemens. End of story as far as pretty much all parties who matter are concerned (Caltrain, Bombardier, Siemens and Stadler).
Re: 1), see 29 July 22:32. I'm too lazy to copy and paste.
DeleteYours is a style of "advocacy" that I just don't get: angry resentment about poor decisions made in the past. Get over it already; anger is blinding and prevents you from seeing straight, for example that the Stadler car shells are wider than the Omneo five-abreast car shells.
Changing train vendors this late in the process will cost several hundred million and is simply not on the menu of feasible options. Advocate for things to be decided in the future, and let go of things decided in the past.
@Anonymous: What about this interior design is "crappy"? The reasons why these trains have so few seats are:
Delete- 2+2 seating chosen when 3+2 would have been possible as well
- more flip-up seats could be installed
- equipment that makes a 6MW power rating possible can't be hidden out of sight (the OMNEO has just 3.2MW in the highest-powered version)
and: TWO ENTIRE cars have NO seats on the lower level "thanks" to all that bike space!
It is simply impossible to design a true high-capacity EMU when all of the above is required.
If we remove the bike space and replace it with one euro-style multipurpose area with additional flip-up seats
(like on this train, scroll down to the pictures: https://www.rmv.de/c/de/linien-netze/fahrzeuge/regionalzuege/twindexx-vario-doppelstock-elektrotriebzuege/twindexx-vario-doppelstock-elektrotriebzug-main-neckar-ried/#group[87761]-5 ),
add 3+2 seating and more flip-up seats at the doors, the 7-car trains easily reach 5.4 seats/m, as Clem wrote already.
All of the electrical equipment that takes away space is needed to make the trains as quick as Caltrain wants them to be. No OMNEO will ever be able to meet the performance required in the RFP.
Correction: Since the additional 7th car will be powered, the new trains will actually have 8MW, which seems pretty crazy compared to the 3.2MW (OMNEO) and 4.6MW (Twindexx Vario) offered by Bombardier (both in their highest-powered Version). The only bilevel train with a similar power rating that I know of is the Siemens Desiro HC (4-car-train with 4MW, only 2 bilevel cars), which was designed specifically for high acceleration and high capacity (yet only 50% bilevel, all traction equipment is hidden in the single-level end cars). This just shows the great job Stadler did archieving the power ratings required without removing the upper level of the power cars like Siemens did on the Desiro HC. In this context, the few seats cannibalised by the electrical equipment on the intermediate floors of the KISS seem like a small price to pay.
Delete@Clem: your assertion that "the Stadler car shells are wider than the Omneo five-abreast car shells" is beyond asinine:
Delete1) Who cares if the EXTERIOR shell size of a KISS is 0.393701 inches wider when the Omneo's ingenious window armrest design increases INTERIOR width by a whopping 7 inches?
2) What is your next brilliant stroke of genius? Special ledges so that passengers can hang out of the windows by their toenails?
I should have known! How could I miss that the fatal flaw with our new trains was the insufficiently ingenious ARMREST DESIGN?!? Thank you for clearing that up.
DeleteGiven that U.S. coaches width is 3100-3200 mm, why is the new EMU carbody narrower?
DeleteBreaking News (NOBODY ever saw that one coming!): https://www.sfexaminer.com/news/federal-monitor-warns-caltrain-electrification-project-faces-two-year-delay/
ReplyDeleteThis is more than enough to justify a dedicated HP siding for San Mateo work. Maybe even buy back their old GP9s... better to have eight 24/7 work crews and single tracking all the way from Trousdale to Hendy than two teams that have to run around everyone at noon and pack it in at midnight.
DeleteOn that point, does anyone know if the work crews on Dumbarton are UP or Caltrain? A quick look at the June construction report shows a gap of essentially no work around Junction.
Well, one reason for this debate is that the current Bombardier Bi-Level cars are extremely space efficient, so nearly anything else will look worse. Consider that Bombardier bi-level has 72 seats on upper deck vs only 52 for Stadler KISS. This is because the bi-level section is much longer and illustrates that key to efficiency is this for each car:
ReplyDelete* Maximize bi-level length
* Minimize single-level length
I don't have schematics, but I'd bet it would appear that Stadler could redesign future KISS models to be more space efficient by extending the upper deck to same length as current Bombardier cars.
One way to REALLY maximize space is by minimizing number of trucks - aka articulation. The car length would have to shrink since spacing between trucks can't get wider without car sticking out more on turns, but for a given length of train, the % of single-deck would decrease. You'd still need need room for power equipment, but that can go above the single-deck areas of what today are non-power cars.
I'm not a fan of 2+3 seating especially when Bombardier demonstrates plenty of capacity with 2+2.
Only the "shorty" EMU cars have 52 seats upstairs. The longer ones have 60 seats, and the H car (eighth car of the consist, not yet ordered) will probably have 132 seats, about the same seating capacity as a Bombardier bilevel.
DeleteThe KISS exists in five different profiles already, the widest of which is the Russian one with 700 seats in a six-car set with five-abreast seating. It was also discussed here back in 2013.
I do not understand why the original plan won't fly. It sounds like the FRA is getting hung up on the door vs. window nomenclature. Until the high doors are activated they essentially function as windows and therefore should be considered windows for the purposes of safety regulations. The fact that the procedure of opening these "windows" during an emergency is different from the standard "tear out the rubber gasket" technique is not relevant.
ReplyDeleteJust design the seat backs to be slightly lower than the bottom of the emergency egress windows so exiting by climbing over the seats is no more difficult than climbing over the threshold of a compliant emergency egress window.
Simple solution with no extra cost.
Pretty sure this exact line of thinking went into the original waiver request. Be sure to read the original documents including the incoming waiver request and the FRA's decision letter.
DeleteInteresting. To summarize the request and response it comes down to:
DeleteCaltrain: Can we treat the non-revenue doors as emergency escape windows?
FRA: Doors are Doors. And doors must comply with ...
Basically FRA ignored the spirit of Caltrain's request. It would have been nice if the FRA could at least explain their rationale to their decision other than just pointing back to the same old existing regs.
Caltrain's chosen approach is a ~$15 million mistake...
ReplyDeleteIsn't this 100% the fault of LTK Engineering Services? They were the ones contracted to "manage" FRA regulatory issues. Presumably the JPB will now get their money refunded, right?
Right: Just like they refunded the JPB for the $3.5M TTCI change order to have the trains tested PROPERLY.
DeleteBreaking News!!!
ReplyDelete"Segment [XX]: CP Lick to Gilroy
• This segment will be upgraded to have two dedicated electrified (25kVAC 60Hz) passenger tracks and one non-electrified track.
• The middle (of 3) track will be provided to allow double stack freight trains (cleared for ‘plate H’) to operate when the non-electrified track is not available.
• This operation will be protected by temporal separation and will not be under the protection of a signalling system – other than only allowing one train in the segment at any one time.
• The electrified tracks will be provided with the HSR signalling system, HSR traction power and HSR communication system.
• The tracks will be installed and maintained to HSR standards.
• This segment will include the Gilroy Maintenance-of-Way facility and will include connection to the local non high-speed railroad network."
https://hsr.ca.gov/docs/programs/track/Part_B-1_TS-1_Industry_Draft_Functional_and_Technical_Requirements.pdf (pp13-14)
PS. "the HSR signalling system" = ATC.
What could possibly go wrong???
It's not that dumb. This is clearly being done to facilitate future CapCor integration into HSR-approved track. Diesel Capcors would run in the center until they're ready for deep integration into the CHSRA system... either through improvements to the Alviso line or routing them over Dumbarton and down the peninsula. When that happens UP would be given a new freight-only line adjacent as compensation as track #3 has OCS installed, then CHSRA trains speed up and down the original center track without affecting Caltrain service on either side.
DeleteThe devil's in the details, namely where UP tracks have to splice in from the south. The best solution here would be to turn Gilroy's service platform into a Caltrain/CapCor island platform while CHSRA wyes in east of Coast MT2. This would make for an interesting structure above 101, due to the Paper Mill lead conflicting any connection south of the freeway.
@aarond
DeleteI think you've got the layout wrong. The non-electrified track is not the center track, but the center track can be used for double-stack freight when necessary.
You are correct, Peter and I stand corrected. UP keeps MT-1 untouched, but CHSRA-1/2 built to the west. Tracks connect between Lewis & Martin where the Gilroy station currently connects through. In this way Gilroy doesn't have to be modified at all, short of a new second platform for NB trains that can also be used for CapCor/Starlights on UP MT-1. Capitol, Blossom, Morgan and San Martin would have to be rebuilt. Diridon #1 would not have any wires.
DeleteAnd the end result is 80 feet between gates @Tennant and Dunne...
DeleteWhat could possibly go wrong???
Paging Clem: How about a "Blended Fail" blog post?
ReplyDeletehttps://www.bizjournals.com/sanjose/news/2019/08/07/caltrain-and-high-speed-rail-have-different-plans.html
DeleteI was about to post that link; that's a good article. It resembles something in my drafts folder that I will eventually finish.
DeleteSounds good. Please consider touching on the I-ETMS/ATC "compatibility" fustercluck which should give the FRA sufficient ammo to rescind the NEPA assignment.
DeleteClem, do you have a link for the proposed plug panel change order? Thanks
ReplyDeleteNo. Unfortunately not everything has a link on the public internet.
DeleteMake a CPRA request. If the change order has been executed, they will need to provide it to you.
DeleteOr you could, Peter (or anyone else). Doing what Clem is doing takes a lot of time and energy and, even though I assume you made the comment with only the best intentions, stuff like that can wear on a tireless non-professional. I was in the same place many years back and eventually being treated like staff on stuff like this will burn someone out.
DeleteI don't assume any poor intentions on your part. I'm just trying to remind everyone that you don't want to kill the Golden Goose.
@Michael, I wasn't telling Clem to make the request. It was meant to be a reply to @anonymous. I was trying to make the same point to @anonymous that you made to me, that if he wants particular information he needs to ask the source for it.
DeleteBurlingame grade sep grant (minor)
ReplyDeletehttps://www.smdailyjournal.com/news/local/burlingame-lands-broadway-grade-separation-grant/article_f77fb5f8-bcaa-11e9-a72d-fb453c3a978e.html
In lighter news, I've always wondered why only SF Tunnel #2 is Quad-tracked. Today, I learned the answer:
ReplyDeleteTunnel 2 is the only one of the five tunnels built with twin bores to accommodate four tracks, although the western bore is currently closed. The western bore was built because a high concrete retaining wall was needed to support a city street running alongside that second tunnel.
(https://www.triposo.com/poi/T__c09569ac6a26#)
Also, curious if there's any value in upgrading the Caltrain line to 90 mph operation after electrification if work required is minimal. From the political angle, would not going straight to 110mph end up burning up the political capitol and leave us stuck at 90 mph. I-ETMS is certified by FRA up to only 90mph, so that jump might be easy once PTC work is complete. (per info from article on IL HSR: https://www.midwesthsr.org/chicago-st-louis-line-much-improved-not-done-yet)
Also, if you go on Google Earth and look at aerials from pre-1960 (before I-280 was built), you'll see that the cut and cover tunnels had the Western Pacific's "mainline" passing above them. Looking NW from the crossing, you can see where the WP went into a tunnel under Potrero Hill. The tunnel has been closed for decades, but you can still see the trace of the line all the way up to around the 101-80 interchange.
DeleteWP had plans once to lay its own rails all the way to SF. A map I once saw seemed to have the line following what became the Bayshore Freeway up most of the Peninsula.
There is very little value in increasing Caltrain top speeds to 110 mph. Higher speeds have diminishing returns, even with high-performing rolling stock. It is far better to speed up the slow bits. There is also an unresolved question about what to do with narrow and crowded platforms when express trains blast through; this is something HSR will have to contend with.
DeleteAre you saying that "HSR" will have to contend with blowing up every single island platform peppered up and down the Peninsula by the San Carlos loony bin?
DeleteThey should all be island platforms!
DeleteNot only do they make more efficient (less redundant) use of platform amenities (benches & TVMs, etc.) ... they're wider, safer, more flexible and support the superior FSSF track & platform layout.
Indeed, after you double the width of the existing yellow safety zone from 2.5 feet to 5 feet from platform edge (possibly even with German-style safety barriers), an island platform that meets Caltrain's minimum design standard width will still have 18 feet of remaining usable space. Not so for a side platform, where Caltrain's existing standards could leave as little as 4.5 feet of usable space.
DeleteIf anything will have to be "blown up" it will be the side platforms.
Here is how Germans eliminate the need to "clear the platform area endangered by the suction" without "doubling the width of the existing yellow safety zone from 2.5 feet to 5 feet from platform edge":
Deletehttps://www.google.com/maps/place/D%C3%BCsseldorf+International+Airport/@51.2924947,6.7866755,35m/data=!3m1!1e3!4m5!3m4!1s0x47b8c82e37d91253:0x5b56f56996d4f455!8m2!3d51.2876146!4d6.7667912
Please note that the white barriers between the slow and fast (SFFS) tracks are made of concrete panels designed to protect passengers from flying debris.
Oh now we’re really blowing things up, unless you keep the island platform and go FSSF. With dividing walls, _S|FF|S_ is no better than F|S_S|F.
Delete"Intermediate station platform configurations must ensure customer safety as trains may operate through or in proximity to the station platform without stopping. Platform layout and station operations will mitigate potential hazards and vulnerabilities and noise from trains running through the station at high-speeds. Turnouts to station tracks will be designed to maintain headways and allow efficient train operations by not slowing or stopping following trains. Because of this, intermediate station passenger platforms will:
Delete Provide off-line HSR passenger platforms allowing for pass-through express services on the dualtrack mainline, except at Fullerton Station.
Provide HSR side platforms with center running tracks as the desirable configuration for operational considerations."
https://hsr.ca.gov/docs/programs/eir_memos/Proj_Guidelines_TM0_3_1_Basis_of_Design_R0_150330_PD_Release.pdf
(Section 4.2.4 Track and Platform Configuration on page 13)
Agreed! Here are the _S|FF|S_ walls at Düsseldorf Flughafen that @Roland is talking about.
DeleteSingle center island platforms (FS_SF) are functionally & operationally superior for Caltrain and its passengers. Instead of isolating NB and SB riders from each other with 2 widely-separated platforms (possibly visually blocked by the walls @Roland suggests) with redundant amenities, they greatly simplify crossing NB & SB Caltrains over (for maintenance-related single-tracking and/or turnbacks without crossing both HSR tracks), eliminating the "wrong platform — missed train" problem confused riders currently suffer during single-tracking.
Why are we discussing barrier walls for Caltrain? I assume that the run-through speed for the Düsseldorf station is going to be much higher than any express train on the Caltrain corridor could ever achieve?
DeleteDüsseldorf Airport is a good analogy for Caltrain. It's only about five miles north of the Düsseldorf Hbf, and because of the density of traffic on the line, I assume top speed through the airport is probably no more than 100mph. It's not on a dedicated high speed line, although many ICE trains both pass through and call at the Airport station.
DeleteDüsseldorf Airport has max speed of 200 km/h. Source: https://geovdbn.deutschebahn.com/isr
Delete"Why are we discussing barrier walls for Caltrain?"
DeleteBecause "Anonymous" ("breaking news", "what could possibily go wrong") Roland has a quite the collection of odd and very counter-factual rail-technical idées fixes.
"Intermediate station platform configurations must ensure customer safety as trains may operate through or in proximity to the station platform without stopping. Platform layout and station operations will mitigate potential hazards and vulnerabilities and noise from trains running through the station at high-speeds. Turnouts to station tracks will be designed to maintain headways and allow efficient train operations by not slowing or stopping following trains. Because of this, intermediate station passenger platforms will:
Delete Provide off-line HSR passenger platforms allowing for pass-through express services on the dualtrack mainline, except at Fullerton Station.
Provide HSR side platforms with center running tracks as the desirable configuration for operational considerations."
https://hsr.ca.gov/docs/programs/eir_memos/Proj_Guidelines_TM0_3_1_Basis_of_Design_R0_150330_PD_Release.pdf
(Section 4.2.4 Track and Platform Configuration on page 13)
Here is a picture of DB Regio double-deckers stopped at the offline passenger platforms. https://www.google.com/maps/place/D%C3%BCsseldorf+Flughafen/@51.2915815,6.7867204,3a,75y,90t/data=!3m8!1e2!3m6!1sAF1QipPCO1_XWmhhsgVz4TEASEjlh0CUh6oOm4W1fh53!2e10!3e12!6shttps:%2F%2Flh5.googleusercontent.com%2Fp%2FAF1QipPCO1_XWmhhsgVz4TEASEjlh0CUh6oOm4W1fh53%3Dw203-h152-k-no!7i4032!8i3024!4m12!1m6!3m5!1s0x47b8c82e37d91253:0x5b56f56996d4f455!2sD%C3%BCsseldorf+International+Airport!8m2!3d51.2876146!4d6.7667912!3m4!1s0x47b8c839540a0acd:0xedcf7780870fe7d4!8m2!3d51.2915831!4d6.7867184
DeleteThe top picture shows an ICE train passing the station at 125 MPH on the mainline (FF)
I stand corrected and thanks for the link to the cool website.
ReplyDelete@Clem "With dividing walls, _S|FF|S_ is no better than F|S_S|F."
ReplyDeleteDid you (conveniently) forget the 2 fences each a minimum of TEN feet off the F track centers?
http://www.caltrain.com/assets/_engineering/engineering-standards-2/criteria/CHAPTER3.pdf Section 3.2 Right-of-Way Fencing on page 3.27
"Did you (conveniently) forget the 2 fences each a minimum of TEN feet off the F track centers?"
DeleteAssuming there's a point to Caltrain's inter-platform fencing, it's to dissaude humans from impulsively (as opposed to premediated suicidally) hopping off a platform and walking across track(s) to reach another platform or the Non-Caltrain Universe.
As such, there's less than zero justification for |F|S_S|F| fencing, especially when -- as nearly always ought to the case on the Caltrain corridor -- the whole station is elevated, and nobody's going to run across two active tracks in order to jump off the side of a bridge.
In contrast, |_SF|FS_| needs the inter-platform fence to dissaude the punters from taking a short-cut from the wrong platform (so easy to be wrong when there are two platforms instead of the logical one, after all) in comparison.
https://caltrain-hsr.blogspot.com/2010/01/football-island.html shows how it works. Not that this will help you. True a decade ago, true today, true ten decades from now. (Good news, everybody!: we're going to be drowing in salt water and desperate for fresh water in just a few short decades!)
The details, in millimetric detail: http://www.pobox.com/users/mly/caltrain-hsr.blogspot.com/FSSF-extra-ROW.pdf
How correctly-configured stations work within the Caltrain ROW, corridor-wide: http://www.pobox.com/users/mly/caltrain-hsr.blogspot.com/FSSF-vs-ROW.pdf
(This is as much fun and as reward as "arguing" actual real-world objective facts with Rick Silver, or Adirondacker6969, or anybody at Parsons Transportation Group, or HNTB ("How Not To Build"), or Parsons-Brinkerhoff, or Caltrain. Idiots gonna idiot. Rent-seekers gonna seek rents.)
Thank you for digging up these oldies-but-goodies.
Delete"Provision shall be made for the installation of protection screens between through tracks and station platforms. This principally involves providing adequate space between main tracks and station tracks at intermediate stations. Provision of 25 feet between track centers will allow for the installation of protection screens, if required."
Deletehttp://www.tillier.net/stuff/hsr/TM-2.2.4-Station-Platform-Geometric-Design-R1-100630.pdf
Roland, Roland, Roland, Roland, this is for 300kmh, not the Caltrain corridor.
DeleteBut since you're on about that decade-old document, do note also "At some stations in shared-use corridors, trains may pass at speeds up to 125 mph on tracks adjacent to a platform."
PS Since you -- and our endlessly ignorant and insular friends at WSP/PBQD/HNTB/PTG/etc friends -- do so love and only recognize English precedents for anything, please do also note that Merry Olde's Stratford International (overbuilding! security theater galore! ridiculously inadequate playtform access!) features no inter-track fencing, and that the slow ("domestic") platform tracks lie inside the fast through tracks. Most suspiciously foreign, wot?
"Saussine (2013) and Rodriguez (2013), among others, have indicated that the distance between tracks plays an important role in ballast flight. The aerodynamic crosswinds created by two trains passing in opposite directions could produce a sufficient force to lift a ballast particle. Amtrak has reported a case (FRA, 2013) which occurred when a Northeast Regional train travelling at 81 mph passed an opposing Acela train travelling at a speed of 101 mph and a closing speed of 182 mph resulted."
Deletehttps://www.fra.dot.gov/Elib/Document/15445
Spotted guidewire reels up on poles today. Specifically the poles near the San Carlos Carls Jr and RWC Burger King. Wondering if their MOW equipment is putting them up or hyrailers (also seen driving on the tracks through SC around noon). Progress is being made. Most of the switcher activity seems to be concerned 25th Av which makes sense.
ReplyDeleteAlso, while at work I got to watch homeless people heckle UP's brakemen which wasn't cool. I realize the port isn't Caltrain's responsibility but eventually someone's going to get a video of it and it'll be an embarrassment for everyone involved.
Latest update from the CV cuckoo factory: "Avenue 8 is 110 feet long and 44 feet at its highest point; Avenue 11 is over 100 feet long and 43 feet at its highest point." https://hsr.ca.gov/about/board/ceo_report.aspx
ReplyDelete@Roland, and so? Photos of the Ave. 8 grade sep bridge suggest the dimensions are plausibly correct .... or were you hinting at some other unstated point?
ReplyDeleteHis unstated point is that the overhead clearance and horizontal extent of many of these grade separations are grossly excessive. Perhaps the HSR people have a Plan B up their sleeve in case HSR doesn't work out, such as triple-stack container trains. Should be plenty of clearance.
Deletehttps://commons.wikimedia.org/wiki/File:Gabarit_AAR_Plate-H.png.
Delete