CalMod 2.0 is a list of future improvements worth about $750M that includes:
- Full fleet conversion to 8-car EMUs ($440M)
- Broadband connectivity ($30M)
- Maintenance facility improvements ($36M)
- Level boarding and platform extensions ($250M)
CalMod 1.1 would consist of just two line items:
1) Lengthen EMUs to 8 cars, for $145M
The EMU fleet for CalMod 1.0 consists of sixteen 6-car trains, with a reduced seating capacity of 558 that has caused much yammering amid the increasing load factors during peak commute hours. Even without a ridership bump from the "new and modern" effect, it is likely these trains will be packed from day one. Now is the time to start doing something about it.
Seating layout for two extra cars (based on Stadler brochure) Two unpowered cars would seat up to 264 passengers. |
The per-train capacity will increase by well over 200 seats per train, back to a level that will mitigate peak hour crowding. However, 8-car EMUs will exceed the length of many of the existing platforms.
2) Extend platforms to a minimum length of 700 feet, for $25M
Platform extensions are relatively cheap to build, especially when you don't need to rebuild the entire length of station platforms as would be needed for level boarding. You can leave vertical circulation (stairs, ramps) and amenities (vending machines, lighting, benches, PA system, departure boards, etc.) alone and just tack on a short length of concrete, and perhaps move a pedestrian crossing. Caltrain excels at building platforms and has done so extensively, pouring some 5 linear miles of platforms over the last 18 years!
The total amount of platform extension required to operate 8-car EMUs is approximately 3500 feet. This figure excludes Hillsdale and South San Francisco, both of which are already slated to be rebuilt to 700 feet. Each foot of platform costs about $7000 to build, on the basis of a typical $10M cost for two 700-foot platforms from past platform reconstruction projects. Therefore, the tab for extending all platforms to 700 feet (for the time being, at their current height of 8 inches) lies in the range of $25M.
Start Planning Now
The bottom line: another $175M or an extra 9% investment over CalMod 1.0 yields an extra 23% peak hour seated capacity for CalMod 1.1. It would be best to start planning for CalMod 1.1 now, and to turn CalMod 2.0 into the big level boarding project for the 2020s. In software parlance, the CalMod 1.1 patch should be applied immediately upon release of CalMod 1.0.